==Chris==
==Chris==
* Geolocation:
* Geolocation:
** Define clear roadmap and B2G QA story.
** {{miss|}} Define clear roadmap and B2G QA story.
** Geofencing WebAPI: work with QC to write API proposal for W3C standardization.
** {{defer|}} Geofencing WebAPI: work with QC to write API proposal for W3C standardization.
* e10s: Focus on add-on compatibility with organized testing and reaching out to add-on developers.
* {{done|}} e10s: Focus on add-on compatibility with organized testing and reaching out to add-on developers.
* Shumway: define milestones and drive to enable Shumway (in Nightly) by end of Q3.
* {{done|}} Shumway: define milestones and drive to enable Shumway (in Nightly) by end of Q3.
* RR2P:
* RR2P:
** Test drive Trello for Geolocation and report experience: [https://trello.com/b/TCwBhEYd/mozilla-geolocation mozilla-geolocation board]
** {{done|}} Test drive Trello for Geolocation and report experience: [https://trello.com/b/TCwBhEYd/mozilla-geolocation mozilla-geolocation board]
** Maybe interview engineering managers about their planning/project tools and write a report.
** {{drop|}} Maybe interview engineering managers about their planning/project tools and write a report.
* Browser Benchmark Automation:
* Browser Benchmark Automation:
** Work with A-Team to build and deploy automation and reporting servers.
** {{done|}} Work with A-Team to build and deploy automation and reporting servers.
** Identify Gecko teams interested in adding new benchmarks.
** {{done|}} Identify Gecko teams interested in adding new benchmarks.


==Erin==
==Erin==
Line 28: Line 28:


==Marco==
==Marco==
* Implement and evaluate V1 Desktop iteration process changes for Iteration 34.2 on Tuesday August 5:
* Implement and evaluate V1 Desktop iteration process changes initiated on Iteration 34.2 (Tuesday August 5):
** Point estimation will be conducted with the whole team asynchronously.
** {{done|}} Point estimation will be conducted asynchronously with the whole team.
** Team will select bugs up to the median value of the velocity range.
** {{done|}} Establish a point cap where the whole team will select bugs up to the median value of the velocity range at the planning meeting.
** Each planning group will have its own production cap based on the specific makeup of the group.
** {{done|}} Each planning group will have its own point cap based on their own production capability.
** Planning meeting begins with the review, removal and/or redistribution of carry over work from the previous iteration.
** {{done|}} 'Review+' bug status will now be considered work in progress and count towards the point cap during the planning meeting.
** The remaining point capacity, up to the median value of the velocity range, is used for new work on the priority list.
* Aim to achieve the following performance gains based on the above mentioned process changes at the conclusion of Iteration 35.2 (Monday September 29):
** Additional work will be included in the iteration once all committed work selected in the planning meeting is at least at the review stage.
** {{done|}} Reduce the average percentage of points selected by 25%.
* Aim to achieve the following performance gains based on the above mentioned process changes at the conclusion of Iteration 35.2 on September 29:
*** Achieved:  average percentage point selection decreased by 28%.
** Reduce the average percentage of points selected by 25%.
** {{done|}} Increase the average percentage of completed work to 75%.
** Improve the average percentage of verified work to 75%.
*** Achieved:  average percentage complete increased from 56% to 76%.
** Reduce the average percentage of carry over work to 25%.
** {{done|}} Reduce the average percentage of carry over work to 25%.
*** The breakdown for the 25% reduction in carry over work aims to be 5% for resolved work awaiting verification and 20% for incomplete Engineering/Design work.
*** Achieved:  average percentage carry over decreased from 44% to 24%.