Connected Devices Weekly Update/2016-10-20: Difference between revisions
Jump to navigation
Jump to search
No edit summary |
No edit summary |
||
Line 12: | Line 12: | ||
! style="background:#00EC00;" | On Target | ! style="background:#00EC00;" | On Target | ||
| | | | ||
* PIB Checkin | * PIB Checkin this Fri, Oct 21 to provide follow up action items from Oct 4 Gate1 review: | ||
** Provide details project plan on 4 main components: Cloud/API, Updates, Device and Hardware. | ** Provide details project plan on 4 main components: Cloud/API, Updates, Device and Hardware. | ||
** Provide updated Architecture diagrams | ** Provide updated Architecture diagrams | ||
** Provide next level budget forecast to 2017 | ** Provide next level budget forecast to 2017 | ||
** | ** Provide detail AWS data hosting costs | ||
* SensorWeb Branding | * SensorWeb Branding | ||
** Checkin meeting with Branding team Oct 26th to review proposed branding framework | ** Checkin meeting with Branding team Oct 26th to review proposed branding framework | ||
Line 22: | Line 22: | ||
** This study will cover UI/ID and installation, unboxing experience, user interaction of setup process and value proposition. | ** This study will cover UI/ID and installation, unboxing experience, user interaction of setup process and value proposition. | ||
* Continuation of weekly 3rd party vendor meetings to support creation of early Sensor hardware development boards by end of Dec 2016. | * Continuation of weekly 3rd party vendor meetings to support creation of early Sensor hardware development boards by end of Dec 2016. | ||
** Upcoming Milestone: | ** Upcoming Milestone: Confirmed key components list and detail Hardware Development Schedule with task and ownership for Dec 2016 | ||
|- | |- | ||
| [[Connected_Devices/Projects/Project_Haiku|Project_Haiku (taking in Project Smart Display)]] | | [[Connected_Devices/Projects/Project_Haiku|Project_Haiku (taking in Project Smart Display)]] |
Revision as of 16:19, 20 October 2016
<< Connected Devices Weekly Updates Home
Program | Passed Gate | Status | Notes | |
---|---|---|---|---|
Project Sensor Web | Cindy/Jean | Gate 1 | On Target |
|
Project_Haiku (taking in Project Smart Display) | Liz/Joe/Mahe | Gate 0 | On Target |
|
Platform and Tools | Sandip/Nicole/Mahe | N/A | On Target |
|
Voice Platform - Deep Speech | Sandip/Nicole | N/A | On Target |
|
Abigail | Preeti/Julie | Gate 0 | On Target |
Prototype Development and Testing
Work Week Update
Schedule
|
Project Magnet | David/Maria | Gate 0 | On Target |
|
HomeWeb | Ben/Mahe | Gate 0 | On Target |
|
GameON! | Candice/Julie | Pre Gate 0 | On Target |
Product Definition
Engineering
|
Lighthouse | Preeti/Julie | Gate 0 | On Target |
Engineering
User Study with Prototype
Schedule
|
PocketID | Francisco | Pre Gate 0 | On Target |
|
3D Printing | Thomas | Pre Gate 0 | On Target |
|
Participation Update | Michael/Brian | -- | On Target |
|
Market Developments Update | Irina |
| ||
Other Announcements / Questions | -- | -- |