'''This week's update'''
* Bulleted list item
*Engineering team on track towards doing Sprint 3 demo Friday, Dec 16:
*# Cloud team: continuation of api implementation and logs of Sensorthings interaction
*# Client team: continuation of the mobile implementation with wireframe options
 
'''Upcoming Tasks'''
* Project planning and Goals for Q1-Q3/2017 during Hawaii Work Week of Dec 5
* Dec 15 - Perform Rapid Risk Analysis (RRA) review with Enterprise Security
 
'''Software Schedule - Dec 16 Milestone:'''
*Firmware: Collect real data from sensors, transmit to cloud

*Cloud: SensorThings API, receive and store sensor readings

*Web: Ability to browse collected sensor readings
'''Hardware Schedule'''
*Dec 19 Development boards ready for Mozilla
|-
|-
| [[Connected_Devices/Projects/Project_Haiku|Project_Haiku]]
| [[Connected_Devices/Projects/Project_Haiku|Project_Haiku]]

Revision as of 17:17, 15 December 2016

<< Connected Devices Weekly Updates Home

Program Passed Gate Status Notes
Project Sensor Web Cindy/Jean Gate 1 On Target

This week's update

  • Engineering team on track towards doing Sprint 3 demo Friday, Dec 16:
    1. Cloud team: continuation of api implementation and logs of Sensorthings interaction
    2. Client team: continuation of the mobile implementation with wireframe options

Upcoming Tasks

  • Project planning and Goals for Q1-Q3/2017 during Hawaii Work Week of Dec 5
  • Dec 15 - Perform Rapid Risk Analysis (RRA) review with Enterprise Security

Software Schedule - Dec 16 Milestone:

  • Firmware: Collect real data from sensors, transmit to cloud

  • Cloud: SensorThings API, receive and store sensor readings

  • Web: Ability to browse collected sensor readings

Hardware Schedule

  • Dec 19 Development boards ready for Mozilla
Project_Haiku Liz/Mahe Gate 1 On Target
  • Bulleted list item
  • Bulleted list item
Platform and Tools Sandip/Nicole/Mahe N/A On Target
  • Bulleted list item
  • Bulleted list item
Voice Platform - Deep Speech Sandip/Nicole N/A On Target

Project VoiceBank at Hawaii

  • 72 contributors
  • 262 sentences submitted

Final Update: Has been officially transitioned to Emerging Technologies

Project Magnet David/Maria Gate 0 On Target
  • Checkin December 21 with PIB with User Study results and Design Direction
  • Scheduling a date for Gate 1 review in early January
  • Overall Hawaii work week was very useful to the team - where we now have a stronger design direction, user journey, and stories beyond the last release.
  • User Validation Study
    • Ran week before Hawaii with 9 people interviewed and testing a mockup
    • Overall had good results and validated hypothesis, but also greatly influenced our design direction and discussion during Work Week.
    • Problem Hypotheses: People have FOMO about knowledge and experiences in the world around them, existing solutions provide useful practical information but are geared towards consumption of goods and services, not gaining knowledge or experiences
    • Experience Strategy: Provide a sense of adventure and progress in the experience, combine the digital and physical worlds in a unique and compelling way, provide visually engaging stories and encourage user-generated content to add value.
    • Problem-solution fit - does our concept have value? We think it does. We are taking stories a bit deeper, and with continuity of a story across different locations. We found that our solution seems very unique and compelling to people who tried it. Can't get the type of content we have elsewhere.
  • Product
    • New User Stories in progress based on a User Journey we worked on in Hawaii. Will release these after some team review.
  • Development
    • Released the new iOS version right before Hawaii. Available in App Store and Google Play. Supports over 1100 deployed points of interest in London and some in San Francisco.
    • Working on technical architecture document for a more 'magazine' style interface.
  • UX
    • Working on new mockups that will support the design direction.
HomeWeb Ben/Mahe Gate 0 On Target
  • Bulleted list item
  • Bulleted list item
GameON! Candice/Julie Gate 0 Moved to Backlog
  • Bulleted list item
  • Bulleted list item
Lighthouse Preeti/Julie Gate 1 On Target

Hawaii Work Week Progress

  • Passed Gate 1!
  • Finished high level planning for post-Gate 1 Phase 1
  • Conducted design and interaction brainstorming
  • Engaged accessibility team

Next Steps (Build-Test-Learn Iterations)

Two phases

  • Phase 1: Mobile App to be completed by end of Q1, 2017, with focus in US (other countries TBD)
  • Phase 2: Dedicated Device app to be completed in Q4, 2017, in English and Spanish and possibility to extend others to MozCommunity

Information Flow Architecture.png

Industrial Design Concepts

  • Wearable
  • Handheld
  • Clip On

Phase 1, Sprint 1 Planning

  • IOS App Dev Ramp-up
  • IOS App Skeleton
  • Draft Requirements Doc
  • Draft UX App Interaction Design
Participation Update Michael/Brian -- On Target
  • Bulleted list item
  • Bulleted list item
Market Developments Update Irina
  • Bulleted list item
  • Bulleted list item
Other Announcements / Questions -- --