Focus for iOS will be following a bi-weekly sprint cadence, so our releases will be schedule driven rather than dictated by feature development progress.  This will give us the ability to respond much more quickly to bug reports and user feedback. Minor releases may be pushed at the end of any sprint as bug fixes and minor changes necessitate, while major releases are targeted following every 3rd sprint.
 
=== Train Schedule - 2018 ===


{| class="wikitable" style="padding:10; font-size:100%; text-align:center;"
{| class="wikitable" style="padding:10; font-size:100%; text-align:center;"
|-
|-
| '''Version''' || '''Sprint Start''' || '''String Freeze/L10N Hand-off''' || '''Feature Complete''' || '''QA hand-off''' || '''QA & L10N App Sign-off''' || Legal Sign-off|| '''Submission''' || '''App Store Content Sign-off''' || '''Release''' || '''Release Themes'''
| '''Sprint''' || '''Sprint Start''' || '''Eng Complete''' || '''QA hand-off''' || '''QA Sign-off''' || '''Submission''' || '''Release''' || '''Release Version & Themes'''
|-
|-
| 2.0 || July 24, 2017 || July 27, 2017 || Aug 4, 2017 || Aug 4, 2017 || Aug 10, 2017 || Aug 10, 2017 || Aug 11, 2017|| Aug 16, 2017  || Aug 17, 2017 || TBC
| Lavender || Jan 8, 2018 || Jan 21, 2018 || Jan 22,2018 || Jan 24, 2018 || Jan 25, 2018 || Upon Approval || V4.1 - Bug fixes
|-
|-
| 2.1 || Aug 7, 2017 || Aug 10, 2017 || Aug 18, 2017 || Aug 18, 2017 || Aug 24, 2017 || Aug 24, 2017 || Aug 25, 2017|| Aug 30, 2017  || Aug 31, 2017 || TBC
| Maroon || Jan 22, 2018 || Feb 4, 2018 || Feb 5, 2018 || Feb 7, 2018 || Feb 8, 2018 || Upon Approval || V4.2 - Bug Fixes
|-
|-
| 2.2 || Aug 21, 2017 || Aug 24, 2017 || Sept 1, 2017 || Sept 1, 2017 || Sept 7, 2017 || Sept 7, 2017 || Sept 8, 2017|| Sept 13, 2017  || Sept 14, 2017 || TBC
| Navy || Feb 5, 2018 || Feb 18, 2018 || Feb 19, 2018 || Feb 21, 2018 || Feb 22, 2018 || Feb 27, 2018 || V5.0 - TBC
|-
|-
| 3.0 || Sept 4, 2017 || Sept 7, 2017 || Sept 15, 2017 || Sept 15, 2017 || Sept 21, 2017 || Sept 21, 2017 || Sept 22, 2017|| Sept 27, 2017 || Sept 28, 2017|| TBC
| Olive || Feb 19, 2018 || Mar 4, 2018 || Mar 5, 2018 || Mar 7, 2018 || Mar 8, 2017 || Upon Approval || V5.1 – Bug Fixes
|-
|-
| 3.1 || Sept 18, 2017 || Sept 21, 2017 || Sept 29, 2017 || Sept 29, 2017 || Oct 5, 2017 || Oct 5, 2017 || Oct 6, 2017|| Oct 11, 2017 || Oct 12, 2017 || TBC
| Plum || Mar 5, 2018 || Mar 18, 2018 || Mar 19, 2018 || Mar 21, 2018 || Mar 22, 2018 || Upon Approval || V5.2 – Bug Fixes
|-
|-
| 3.2 || Oct 2, 2017 || Oct 5, 2017 || Oct 13, 2017 || Oct 13, 2017 || Oct 19, 2017 || Oct 19, 2017 || Oct 20, 2017 || Oct 25, 2017 || Oct 26, 2017 || TBC
| Quartz-grey || Mar 19, 2018 || April 1, 2018 || April 2, 2018 || Apr 4, 2018 || Apr 5, 2018 || Apr 10, 2018 || V6.0 - TBC
|-
|-
| 4.0 || Oct 16, 2017 || Oct 19, 2017 || Oct 27, 2017 || Oct 27, 2017 || Nov 2, 2017 || Nov 2, 2017 || Nov 3, 2017 || Nov 8, 2017 || Nov 9, 2017 || TBC
| Royal blue || Apr 2, 2018 || Apr 15, 2018 || Apr 16, 2018 || Apr 18, 2018 || Apr 19, 2018 || Upon Approval || V6.1 – Bug Fixes
|-
|-
| 4.1 || Oct 30, 2017 || Oct 26, 2017 || Nov 3, 2017 || Nov 3, 2017 || Nov 9, 2017 || Nov 9, 2017 || Nov 10, 2017 || Nov 15, 2017 || Nov 16, 2017 || TBC
| Seashell || Apr 16, 2018 || Apr 29, 2018 || Apr 30, 2018 || May 2, 2018 || May 3, 2018 || Upon Approval || V6.2 – Bug Fixes
|-
|-
| 4.2 || Nov 13, 2017 || Nov 9, 2017 || Nov 17, 2017 || Nov 17, 2017 || Nov 23, 2017 || Nov 23, 2017 || Nov 24, 2017 || Nov 29, 2017 || Nov 30, 2017 || TBC
| Teal || Apr 30 2018 || May 13, 2018 || May 14, 2018 || May 16, 2018 || May 17, 2018 || May 22, 2018 || V7.0 - TBC
|-
|-
| 5.0 || Nov 27, 2017 || Nov 23, 2017 || Dec 1, 2017 || Dec 1, 2017 || Dec 7, 2017 || Dec 7, 2017 || Dec 8, 2017 || Dec 13, 2017 || Dec 14, 2017 || TBC
| Umber || May 14, 2018 || May 27, 2018 || May 28, 2018 ||May 30, 2018 || May 31, 2017 || Upon Approval || V7.1 – Bug Fixes
|-
|-
| 5.1 || Dec 11, 2017|| Dec 7, 2017 || Dec 15, 2017 || Dec 15, 2017 || Dec 21, 2017 || Dec 21, 2017 || Dec 22, 2017 || TBC || TBC || TBC
| Violet || May 28, 2018|| June 10, 2018 || June 11, 2018 || June 13, 2018 - TBC || June 14, 2018 - TBC || TBC due to SFO All-Hands


|}
|}
=== Legend of Milestones ===
*'''Sprint Start''' - Development work kicks off based on priorities identified, and commitments made in the last planning meeting, and continues for a period of two weeks.
*'''QA hand-off''' - A first/potential candidate build is created by Engineering, and passed to QA for final Acceptance Testing.  (This is required/performed in addition to the ongoing feature testing which takes place throughout the development cycle, as particular items land.)
*'''QA Sign-off''' - Automated testing, as well as manual feature testing have been completed at a level determined to be sufficient for the release by QA.  Any issues identified during acceptance testing, which were deemed to be blockers have been resolved, and the fixes verified by QA.
*'''Submission''' -
*'''Release''' -