= December 9, 2008 =
= December 9, 2008 Meeting Notes =
== Attendees ==
Rick Reitmaier, Dan Schaffer, Dan Smith, Brent Baker, Leslie Lewis, Rob Borcic, Moh (Intel), Tom Harwood, Tom Reilly,  Steven Johnson, Rudolph, Shengnan (Intel)
 
== Agenda Topics ==
* PPC Update (Dan Schaffer)
* Next Iteration (Dan Smith)
 
== Action Items ==
* Dan Schaffer to send details of PPC Test Results to tamarin-devel distribution list - DONE
* All code that needs to get into the next release of TC needs to be checked in and tested by 12/16/08. Next release on 12/22/08.
 


== Attendees ==
== Meeting Discussion Notes ==
 
=== Mac PPC Performance (switch from MIR to LIR) ===
* PPC pushed and landed late last week
* 8% faster
* 6% lower memory
* Only some sun spider tests showed some slower times
* All other tests across te board faster (JSBoard, SciMark – 20% faster)
* All acceptance tests are pass
* Looks good - We can pull the plug on MIR


* Intel: Shengnan
=== Next iteration ===
* Adobe: Edwin Smith, Steven Johnson, Tom Harwood, Leslie, Lars, Jeff Dyer, Rob Winchell, Rob Borcic, Trevor Baker, Dan Schaffer, Brent Baker, Dan Smith, Rick Reitmaier, Rishit Shah
** We will plan to do drops approx 1/month for TC
** Next drop to be done on Monday, 12/22
** All code changes be submitted and tested by 12/17
** 3 days is enough to shakedown and certify the build
** Lars and Trevor will work together to get the build out


== Agenda Items Discussed ==