| '''Next meeting's Agenda Items (1/6/09):''' | | '''Next meeting's Agenda Items (3/17/09):''' |
| * Status of open work items for current release | | * Canceled |
| * Discuss sprint planning process (Dan Smith)
| |
|
| |
|
|
| |
|
|
| |
|
| = December 16, 2008 Meeting Notes = | | |
| | = January 27, 2009 Meeting Notes = |
| == Attendees == | | == Attendees == |
| Rick Reitmaier, Dan Schaffer, Dan Smith, Brent Baker, Leslie Lewis, Rob Borcic, Moh (Intel), Tom Harwood, Tom Reilly, Steven Johnson, Rudolph, Shengnan (Intel)
| | Jeff, Steven, Brent, Tom, Dan Schaffer, Rick Reitmaier, Rob Winchell, Moh |
| | |
| == Agenda Topics == | | == Agenda Topics == |
| * Release Update | | * Status Updates |
| * Next Sprint
| |
|
| |
|
| == Action Items == | | == Meeting Discussion Notes == |
| * When we get back on 1/5/09, let’s see where we are with outstanding features and on that day we can pick when we can do the integration. We can plan to do a release the week of 1/5
| | === Status Updates === |
|
| |
|
| == Meeting Discussion Notes ==
| | Jeff: |
| === Release Update ===
| | * Checked in a verifier refactoring. Some cleanup needed, but wanted to get it in. |
| * Should we delay? Status of current work items below:
| | * Put in a pipeline architecture where all code generators are driven off of api (similar to backend nanojit api) |
| * X64 (Edwin/Rick) | |
| ** Changes for LIR are 80%
| |
| ** PPC passing many tests
| |
| ** X64 almost working
| |
| ** Need some cleanup time
| |
| * ARM patches
| |
| ** still outstanding
| |
| ** Close but risky for the end of the week
| |
| * Out of Memory | |
| ** 2 days away from having infrastructure ready for testing
| |
| ** Approx 1 week of testing
| |
| * When we get back on 1/5/09, let’s see where we are with outstanding features and on that day we can pick when we can do the integration. We can plan to do a release the week of 1/5
| |
|
| |
|
| === Next Iteration Planning ===
| |
| * Start next iteration on 1/12.
| |
| * Grooming product backlog
| |
| * Forming teams
| |
| * Ed and Lars will help to groom product backlog
| |
|
| |
|
| === Global Optimizer (Tom Harwood) ===
| | Steven |
| * Working with Scott Peterson’s LLVM integration | | * Spot bug fixing |
| * In POC point
| |
| * Tom is turning it into a plug-in for GO, once this is done Tom will add a product backlog for GO and quantify work to get LLVM plugin
| |
| * Add GO items to existing Product Backlog
| |
| * There is an AS buildbot that runs GO, there are about 300 failures in acceptance tests, performance tests – ratio is about 10% faster, memory 6% lower, abc code about 6% smaller
| |
|
| |
|
| === Verifier (Jeff) ===
| | Dan Schaffer |
| * Going well | | * Ecma 3 data acceptance tests |
| * Patch by end of next week | | * If anyone sees any failures, send Dan Schaffer an email |
| * As soon as there is a release, he would like to have it reviewed and integrated
| | * There may still be some lurking problems |
| * Once it is integrated, he will work on input verifier logic | |
|
| |
|
| | Tom Harwood |
| | * Global optimizer stopped working on this for now |
| | * Starting to work on verifier and code generators instead |
| | * Jeff’s change broke GO code |
| | * Tom filed a bug on that. Copy Jeff on that but. |
|
| |
|
|
| |
|
| = Older meetings = | | = Older meetings = |
| | * [[Tamarin:WeeklyUpdates/2009-01-27|January 27, 2009]] |
| | * [[Tamarin:WeeklyUpdates/2009-01-013|January 13, 2009]] |
| | * [[Tamarin:WeeklyUpdates/2009-01-06|January 6, 2009]] |
| * [[Tamarin:WeeklyUpdates/2008-12-16|December 16, 2008]] | | * [[Tamarin:WeeklyUpdates/2008-12-16|December 16, 2008]] |
| * [[Tamarin:WeeklyUpdates/2008-12-09|December 9, 2008]] | | * [[Tamarin:WeeklyUpdates/2008-12-09|December 9, 2008]] |