(Created page with "= 2.1 = * QA asked for freeze to push out to next week, so ** Freeze 7/19 ** Release 7/21 * I have added in the content crash related bugs, which need doing pretty urgently. Th...")
 
 
(One intermediate revision by the same user not shown)
Line 4: Line 4:
** Release 7/21
** Release 7/21
* I have added in the content crash related bugs, which need doing pretty urgently.  This is the critical focus of this release
* I have added in the content crash related bugs, which need doing pretty urgently.  This is the critical focus of this release
* bugs
* [https://bugzilla.mozilla.org/buglist.cgi?classification=Server%20Software&query_format=advanced&component=Socorro&target_milestone=2.1&product=Webtools 2.1 bugs]


= 2.2 =
= 2.2 =
* Focus of 2.2 is changing the aggregation criteria, as per yesterday's meeting
* Focus of 2.2 is changing the aggregation criteria, as per yesterday's meeting
** [etherpad]
** [http://etherpad.mozilla.com:9000/rapid-release-reports-socorro etherpad]
* bug list not finalized, need to file some, but
** [https://bugzilla.mozilla.org/buglist.cgi?classification=Server%20Software&query_format=advanced&component=Socorro&target_milestone=2.2&product=Webtools 2.2 bugs]
* Timeline
* Timeline
** Needed for Fx6 final beta
** Needed for Fx6 final beta
Line 17: Line 19:
= ES =
= ES =
* Status as per plan (dre):
* Status as per plan (dre):
** light up prod ES boxes - by July 15
** light up prod ES boxes - was by July 15 - now TBD, another week?  Hardware problems.
** turn on two processors, watch perf for 24 hours - sometime in test period, before July 15
** turn on two processors, watch perf for 24 hours - sometime in test period, before July 15
** turn on rest of processors, watch for another 2-3 days
** turn on rest of processors, watch for another 2-3 days
** backfill data - run manually once all processors switched over
** backfill data - run manually once all processors switched over
** turn on webapp - aim for by 22nd, long window by the end of the month  
** turn on webapp - aim for by 22nd, long window by the end of the month


= Other issues =
= Other issues =
* Onsite Aug 8-12.  Don't plan too many meetings.  This is a sprint week.
* Onsite Aug 8-12.  Don't plan too many meetings.  This is a sprint week.
* github/release stuff: laura and rhelmer discussed, working on doc which will be circulated.  We won't change process until rhelmer is back on deck.