Websites/Snippets/Impressions/Weekly-Status-Reports/2012-02-03: Difference between revisions

From MozillaWiki
Jump to navigation Jump to search
 
(12 intermediate revisions by the same user not shown)
Line 29: Line 29:
| class="header" style="background:white;| Comment
| class="header" style="background:white;| Comment
|-
|-
| '''OVERALL STATUS''' || X ||  ||  ||  ||
| '''OVERALL STATUS''' || X ||  ||  ||  ||  
|-
|-
| Budget ||   ||  ||  || X ||   
| Schedule || X ||  ||  ||   ||   
|-
|-
| Schedule || X ||  ||  ||  ||
| Scope || X ||  ||  ||  ||  
|-
|-
| Scope || X ||  ||  ||   ||   
| Budget ||   ||  ||  || X ||   
|}
|}
<!-- /Status -->
<!-- /Status -->
Line 51: Line 51:
| Original || Current
| Original || Current
|-
|-
| N/A || N/A
| Jan 20 || Jan 20
| March 5 || N/A
| March 7 || N/A
|}
|}


Line 89: Line 89:
| class="header" | Comments
| class="header" | Comments
|-
|-
| Create Mana Item For Zeus  || cshields / bsternthal || 02/01/2012 || N/A ||
| Create Mana Item For Zeus  || cshields / bsternthal || 02/06/2012 || N/A ||
|-
|-
| BS to workout/send milestone schedule || bs/team || 02/06/2012 || N/A ||
| Workout/confirm milestone schedule || bs/team || 02/06/2012 || N/A ||
|-
|-
| Collection Testing On Staging  ||  bsternthal || 02/11/2012 || N/A ||
| Collection Testing On Staging? ||  bsternthal || 02/11/2012 || N/A ||
|-
|-
|}
|}
Line 110: Line 110:
| class="header" | Status
| class="header" | Status
|-
|-
| Define Hardware Reqs & Order || IT || High || 01/27/2012 || [https://bugzilla.mozilla.org/show_bug.cgi?id=698815 698815] || Resolved
| <del>Define Hardware Reqs & Order</del> || IT || High || 01/27/2012 || [https://bugzilla.mozilla.org/show_bug.cgi?id=698815 698815] || Resolved
|-
|-
|}
|}
<!-- /MAJOR ISSUES -->
<!-- /MAJOR ISSUES -->


===== <span style="color:white">Project Milestones</span> =====
===== <span style="color:white">Project Milestones</span> =====
Line 137: Line 130:
| colspan="8" | '''WebDev'''
| colspan="8" | '''WebDev'''
|-
|-
| &nbsp;&nbsp; Interface & JS ||MK ||2/29 || || ||[https://bugzilla.mozilla.org/show_bug.cgi?id=690881 690881] ||
| &nbsp;&nbsp; Interface & JS ||MK ||2/27 - 3/1 || || ||[https://bugzilla.mozilla.org/show_bug.cgi?id=690881 690881] ||
|-
|-
| colspan="8" | '''Privacy'''
| colspan="8" | '''Privacy'''
Line 145: Line 138:
| colspan="8" | '''Security'''
| colspan="8" | '''Security'''
|-
|-
| &nbsp;&nbsp; Security Review ||SM ||3/2 || || ||[https://bugzilla.mozilla.org/show_bug.cgi?id=723596 723596] ||
| &nbsp;&nbsp; Security Review ||YB ||3/1 - 3/5 || || ||[https://bugzilla.mozilla.org/show_bug.cgi?id=723596 723596] ||
|-
|-
| colspan="8" | '''QA'''
| colspan="8" | '''QA'''
|-
|-
| &nbsp;&nbsp; QA Review ||SM ||3/2 || || ||[https://bugzilla.mozilla.org/show_bug.cgi?id=723600 723600] ||
| &nbsp;&nbsp; Selenium Tests ||SD ||2/21 - 2/24 || || ||[https://bugzilla.mozilla.org/show_bug.cgi?id=724114 724114] ||
|-
| &nbsp;&nbsp; QA Review ||SD ||3/1 - 3/5 || || ||[https://bugzilla.mozilla.org/show_bug.cgi?id=723600 723600] ||
|-
|-
| colspan="8" | '''IT'''
| colspan="8" | '''IT'''
Line 157: Line 152:
| colspan="8" | '''Metrics'''
| colspan="8" | '''Metrics'''
|-
|-
| &nbsp;&nbsp; TBD || || || || || ||
| &nbsp;&nbsp; Stage Dashboard ||AP ||4/15 || || || ||
|-
|-
|}
|}
<!-- /PROJECT MILESTONES -->
<!-- /PROJECT MILESTONES -->

Latest revision as of 00:17, 7 February 2012

Summary
DOC VERSION: 1.0 STATUS REPORT AS OF: Feb 03, 2012
AUTHOR: Benjamin Sternthal
TPM: Benjamin Sternthal
PROJECT SPONSOR: Laura Forrest
PROJECT WIKI: Websites/Snippets/Impressions
Status
1. STATUS
Status Item On Track Caution Crisis N/A Comment
OVERALL STATUS X
Schedule X
Scope X
Budget X
Schedule & Budget
2. SCHEDULE
Start Date Completion Date
Original Current Original Current
Jan 20 Jan 20 March 7 N/A
3. BUDGET
Original Current
Cost Of Work
Performed
Estimated
Actual Cost
Variance
at
Completion
N/A N/A N/A N/A
Recent Accomplishments
4. RECENT ACCOMPLISHMENTS
  • Mkelly availability tracking to mid-late feb to add to interface. PTO week of the 20th so prob week of the 27th
Upcoming Tasks
5. UPCOMING TASKS
Task Owner Due Date Bugzilla Comments
Create Mana Item For Zeus cshields / bsternthal 02/06/2012 N/A
Workout/confirm milestone schedule bs/team 02/06/2012 N/A
Collection Testing On Staging? bsternthal 02/11/2012 N/A
Major Issues
6. MAJOR ISSUES, CONCERNS & IMPACTS (* = new)
Issue Description Owner Priority Date Due Bugzilla Status
Define Hardware Reqs & Order IT High 01/27/2012 698815 Resolved
Project Milestones
7. PROJECT MILESTONES
Issue Owner Target
Completion
Date
Revised
Completion
Date
Acutal
Completion
Date
Bugzilla Status
WebDev
   Interface & JS MK 2/27 - 3/1 690881
Privacy
   Review Collection Data TBD 2/17 723589
Security
   Security Review YB 3/1 - 3/5 723596
QA
   Selenium Tests SD 2/21 - 2/24 724114
   QA Review SD 3/1 - 3/5 723600
IT
   Confirm & Document Zeus Solution CS 2/17 698815
Metrics
   Stage Dashboard AP 4/15