The main focus of [[Gaia]] Milestone 2.1 is to have a developer phone usable on a day-by-day basis. We'll continue to make front-end improvements that reflect | The main focus of [[Gaia]] Milestone 2.1 is to have a developer phone usable on a day-by-day basis. We'll continue to make front-end improvements that reflect the device's capabilities. | ||
The plan is to land all P1 bugs listed below for the 2.1 milestone. | |||
= Timeline = | = Timeline = |
Revision as of 00:29, 29 February 2012
Objectives
The main focus of Gaia Milestone 2.1 is to have a developer phone usable on a day-by-day basis. We'll continue to make front-end improvements that reflect the device's capabilities.
The plan is to land all P1 bugs listed below for the 2.1 milestone.
Timeline
The target date is the 9 march 2012.
Projects
List of projects for the Milestone 2.1
Description | Priority | Status | Details | Owner | Strings | Images | Bugs |
Use MozContacts | P1 | RUNWAY | details | Etienne | yes | yes | |
Calendar app | P2 | RUNWAY | details | no | no | ||
Email app | P1 | RUNWAY | details | no | no | ||
Dial History | P2 | INFLIGHT | details | Etienne | no | yes | |
Window Manager Stability | P1 | TAKEOFF | details | David | no | no | |
Tasks Manager | P2 | TAKEOFF | details | no | yes | ||
Sms Database | P1 | TAKEOFF | details | Tim | no | no | |
Sms Homescreen | P1 | TAKEOFF | details | Tim | no | yes | |
Sms Multiline | P2 | TAKEOFF | details | no | no | ||
Network Manager (wifi and 3G) | P1 | RUNWAY | details | Ben | yes | yes | |
Tests | P1 | TAKEOFF | details | ALL!!! | no | no | |
Camera UI | P3 | TAKEOFF | details | no | yes | ||
Ring Tone And Volume | P1 | RUNWAY | details | Fabien | yes | yes | |
Real Fullscreen | P2 | TAKEOFF | details | no | no | ||
UI Transitions/animations | P3 | RUNWAY | no | no | |||
Settings UI | P2 | RUNWAY | details | yes | yes | ||
Orientation Support | P2 | TAKEOFF | details | no | no | ||
Geolocation Support | P3 | TAKEOFF | details | no | no | ||
Localization Support | P2 | RUNWAY | details | yes | no | ||
Mobilize our messages/dialogs | P4 | RUNWAY | details | yes | yes | ||
Form Assistant | P3 | RUNWAY | details | yes | no | ||
Intents | P2 | TAKEOFF | details | yes | no |
Status Legend:
- RUNWAY - Waiting for design or initial planning
- TAKEOFF - Ready for work to begin
- INFLIGHT - Work is in progress. Patches should be in bugs.
- LANDED - Work has finished and is in the product.