Program Management/Weekly-Status-Reports/2012-11-27: Difference between revisions

m
 
(3 intermediate revisions by 3 users not shown)
Line 2: Line 2:
* Goal setting process
* Goal setting process
* Update on Metro
* Update on Metro
* Update on Marco Mucci


==Dietrich==
==Dietrich==
Line 8: Line 9:


==Lawrence==
==Lawrence==
* Platform technical roadmap
** Met with bz, jpr, roc, dbaron, dmandelin to discuss platform technical roadmap
** Working on platform architectural diagram to communicate the story
* B2G
** Updated dashboard to respond to new Gaia components
* Performance
** Continue to push on remaining Telemetry enabled-by-default blockers
* Mobile Web Compat
** Still working on updates for UA detection frameworks/products
** Still working to communicate issues with Vimeo and BrightCove
** Deep dive site investigation in {{bug|811421} - next part of Webkit aliasing analysis


==Martin==
==Martin==
* Last week was off site with a games partner.
* Worked on updating prediction model with linear projections that monitors last 6 weeks ongoing.
* Worked on javascript version of prediction model to automate the process going forward.


==Michael==
==Michael==
*Working on FFOS - ZTE schedule: target launch end of May
*Need a plan to close remaining 'Open' features
*Working with TEF on timeline activity metrics
*Working with TEF on FFOS schedule risks