* Administrative stuff | * Administrative stuff | ||
** MV office space | |||
* Q2 goals - https://wiki.mozilla.org/Program_Management/Firefox/2013-Q2-Goals | * Q2 goals - https://wiki.mozilla.org/Program_Management/Firefox/2013-Q2-Goals | ||
* Call for resources to help with FFOS | * Call for resources to help with FFOS | ||
Line 12: | Line 13: | ||
==Lawrence== | ==Lawrence== | ||
* Web compat | |||
** Hiring | |||
** Community plans | |||
** UA policy | |||
** Dashboards and project plans | |||
* Performance | |||
** Completed first draft of initial project goals | |||
** First run of performance monthly meeting | |||
* Git migration | |||
** Finished conversation with GitHub | |||
** Proposed approach next week | |||
* More interviewing for platform pm | |||
==Martin== | ==Martin== | ||
==Michael== | ==Michael== | ||
*This Week: | |||
** Update FFOS Version Map Home page with Sheila | |||
** Sponsor's meeting Thursday (FFOS escalations) | |||
** Update Gantt for LGE (v1.1) | |||
==Marco== | ==Marco== | ||
* Iteration #6 ends today - 74 points completed. | |||
* Status report to be released Friday May 3. | |||
* Product Manager revised the priority levels of the feature stories in the Story Backlog. | |||
* Best and Worst Case release forecast scenarios will be added to status reports from Iteration #6 moving forwards. | |||
==Sheila== | ==Sheila== | ||
Line 28: | Line 49: | ||
** Look at how +/- triage changes throughout release cycle | ** Look at how +/- triage changes throughout release cycle | ||
* Helping organize coaching session for other teams that want to move to agile | * Helping organize coaching session for other teams that want to move to agile | ||
==Tauni== | |||
* B2G code merge on schedule (end of this week) | |||
** Please contact me if Identity can support the request to assist with Gaia bugs | |||
* Yahoo BigTent (proxy IdP) patch this week for email alias' | |||
* PiCL - Fennec Technical kick-off scheduled this week | |||
* Identity Work Week May 6 - 10, Vancouver | |||
* Identity 2013 [https://wiki.mozilla.org/Identity Roadmap] |