==Agenda== | ==Agenda== | ||
* New PM - Chris Peterson | * New PM - Chris Peterson | ||
* Summit update (Lawrence) | |||
* Tribe sessions | * Tribe sessions | ||
* Meeting next week | * Meeting next week | ||
* Headcount update | * Headcount update | ||
* Stability work week (Aug 19-23 MV) | * Stability work week (Aug 19-23 MV) | ||
* FHR update | * FHR update | ||
==Candice== | ==Candice== | ||
* FFOS Agile rollout update | |||
* Work weeks - functional teams in progress | |||
* Next steps (Candice, Martin, Marco, Sheila) | |||
==Dietrich== | ==Dietrich== | ||
* Open Source Bridge this week, Firefox OS hacking event tonight | |||
* LG QE3 workweek in Taipei June 24 - 28 | |||
* LG QE3 ending this week, up to 73 bugs right now | |||
==Erin== | ==Erin== | ||
*Roadmap management | |||
*Fx22 GA readiness | |||
*Shumway | |||
*WebRTC (ramping up) | |||
*Dynamic Snippets (risk management) | |||
==Lawrence== | ==Lawrence== | ||
* Summit planning assembly | |||
* Performance project planning for front-end teams | |||
* Mobile Web compat hiring | |||
==Martin== | ==Martin== | ||
Line 37: | Line 52: | ||
==Tauni== | ==Tauni== | ||
* focused on leveling resources this week | |||
* PTO July 22 - 26 |
Latest revision as of 17:18, 18 June 2013
Agenda
- New PM - Chris Peterson
- Summit update (Lawrence)
- Tribe sessions
- Meeting next week
- Headcount update
- Stability work week (Aug 19-23 MV)
- FHR update
Candice
- FFOS Agile rollout update
- Work weeks - functional teams in progress
- Next steps (Candice, Martin, Marco, Sheila)
Dietrich
- Open Source Bridge this week, Firefox OS hacking event tonight
- LG QE3 workweek in Taipei June 24 - 28
- LG QE3 ending this week, up to 73 bugs right now
Erin
- Roadmap management
- Fx22 GA readiness
- Shumway
- WebRTC (ramping up)
- Dynamic Snippets (risk management)
Lawrence
- Summit planning assembly
- Performance project planning for front-end teams
- Mobile Web compat hiring
Martin
Michael
- PTO this week
- Taipei Jul 1-3
Marco
- Team working on Iteration #9 - June 12, 2013 - June 25, 2013
- QA working on testing IT #0 - IT #8 - 18 bugs remain to be tested.
- Metro Test Day scheduled for Friday June 28.
Sheila
- Still more interviews for Payments PM
- FFOS
- 1.2 scoping - working with Faramarz/Chris Lee on getting "gut checks" for feature list
- Helping with roll-out plan - documentation, meetings, presentations
- Working with Larissa on updates for weekly sponsors meetings
- FHR
- Working with John Jensen on transitioning meetings
Tauni
- focused on leveling resources this week
- PTO July 22 - 26