Line 13: | Line 13: | ||
==Firefox Metro== | ==Firefox Metro== | ||
<p> </p> | <p> </p> | ||
* '''Total Goals:''' | * '''Total Goals:''' 13 | ||
* '''Completed Goals:''' 4 | * '''Completed Goals:''' 4 | ||
* '''Missed Goals:''' 0 | * '''Missed Goals:''' 0 | ||
Line 30: | Line 30: | ||
** Maximum Average Fail Rate - 11% | ** Maximum Average Fail Rate - 11% | ||
** Minimum Average Coverage Rate - 85% | ** Minimum Average Coverage Rate - 85% | ||
* Conduct a second Metro Test Day by the conclusion of Q3. | * Conduct a second Metro Test Day by the conclusion of Q3. | ||
<p> </p> | <p> </p> |
Revision as of 21:04, 12 August 2013
Firefox Desktop
- TBD.
Firefox Android
- Product Announcements test and subsequent hand-off to Winston's team (hopefully)
- Privacy and Security reviews for
- Project Plan for Shumway
- Manage risk for all features shipping in Fx23, Fx24
- Mobile Work Week
- Help manage WebRTC automation plan of attack
- Check out Webmaker.org and see where I can get involved, even if is just to help test
Firefox Metro
- Total Goals: 13
- Completed Goals: 4
- Missed Goals: 0
Project Management
- [DONE] Conduct a review of the Story Backlog and revise the priority levels of feature stories by the conclusion of Q3.
- Completed at the end of Iteration #11 on July 26.
- All P3 Feature Stories and Defect/Change Stories are no longer considered a blocking bug and not mandatory for a V1 release.
- All P3 Feature Stories and Defect/Change Stories have been moved to V2.
- All new Feature Stories and Defect/Change Stories will now be triaged for inclusion as part of the Metro Preview as well as priority ranking.
- Maintain 'planning' backlog at no more than 10 items at the conclusion of Q3.
Quality Management
- Maintain quality performance indicators (across Iterations #10 - #14) at the following levels by the conclusion of Q3:
- Minimum Average Pass Rate - 89%
- Maximum Average Fail Rate - 11%
- Minimum Average Coverage Rate - 85%
- Conduct a second Metro Test Day by the conclusion of Q3.
Product Development
- [DONE] Conclude Development Iteration #10 and Deliver Release Build to Product Manager and QA Department.
- Completed at the end of Iteration #10 on July 12.
- [DONE] Conclude Development Iteration #11 and Deliver Release Build to Product Manager and QA Department.
- Completed at the end of Iteration #11 on July 26.
- Conclude Development Iteration #12 and Deliver Release Build to Product Manager and QA Department.
- Conclude Development Iteration #13 and Deliver Release Build to Product Manager and QA Department.
- Conclude Development Iteration #14 and Deliver Release Build to Product Manager and QA Department.
- Conclude Development Iteration #15 and Deliver Release Build to Product Manager and QA Department.
- [DONE] Identify the feature stories, defects and changes required for a Firefox Metro Preview Release consisting of start (top sites, bookmarks, and history), basic navigation, tabbed browsing, smooth panning, scrolling and zooming.
- Completed during Iteration #12 - View Metro Preview Release Backlog
- Develop the initial development complete forecasts (expected, pessimistic and optimistic) for the Firefox Metro Preview Release.
Team Performance
- Establish a minimum median velocity of 50 (Expected Date of Completion) and an actual velocity range that falls between 46 (Pessimistic Date of Completion) and 63 (Optimistic Date of Completion) by the conclusion of Iteration #15.
Firefox OS
- TBD.
Platform
- TBD.
Mobile Web Compatibility
- TBD.
Program/Project Management