* User migration is ready to be tested in dev.
* Shouldn't require downtime, but will be after the production h/w is done.
* The production systems will be available from the 5th for server load testing.
* Functional testing against production from the 5th.
* Load testing will happen the week after against the production.
* Observations will happen from the 11th using utest.
* Security evaluations will also happen the same week.
* Server blocker: async user creation using gearman.
* 1.3pre1 to ship on Thursday to get early feedback from Friday's test day.
** New Firefox UI, including first run UX issues.
** Known functional bug fixes.
** Won't include code audit done and unit tests.
* All code blockers will be done by April 30 (will not include unit tests).
* Security evaluations will start on the client from the 3rd.
* '''AI:''' mrz will add HA testing to the qa checklist (what happens when we lose a cable etc)
* '''AI:''' We need to triage add-on reviews. Ragavan and Justin to work on that.
* '''AI:''' We need a support plan. Ragavan and Tenser to work on that.
* '''AI:''' Figure out if we can make string changes to the name for 1.3 or if we will need a 1.4.
* iPhone client is about 6-8 weeks away.
canmove, Confirmed users