Firefox OS/OneDotFourTracking: Difference between revisions
Jump to navigation
Jump to search
Praghunath (talk | contribs) |
Praghunath (talk | contribs) |
||
Line 2: | Line 2: | ||
==1.4 Schedule== | ==1.4 Schedule== | ||
* Milestones Schedule | * Milestones Schedule | ||
#Sprint 1 – feature dev:: 2/3/14 – 2/14/14 | #Sprint 1 – feature dev :: 2/3/14 – 2/14/14 | ||
#Sprint 2 – feature dev:: 2/17/14 – 2/28/14 | #Sprint 2 – feature dev :: 2/17/14 – 2/28/14 | ||
#Sprint 3 – feature dev:: 3/3/14 – 3/14/14 | #Sprint 3 – feature dev :: 3/3/14 – 3/14/14 | ||
#Sprint 4 – Planning (1.5):: 3/17/14 – 3/28/14 | #Sprint 4 – Planning (1.5) :: 3/17/14 – 3/28/14 | ||
#Sprint 5 – stabilization:: 4/1/14 – 4/11/14 | #*Sprint 4 - 1.4 stabilization begins | ||
#Sprint 6 – stabilization:: 4/15/14 – 4/25/14 | #Sprint 5 – stabilization :: 4/1/14 – 4/11/14 | ||
#Internal feature complete:: 3/14/2014 | #Sprint 6 – stabilization :: 4/15/14 – 4/25/14 | ||
#Hard string Freeze:: 3/28/2014 | #Internal feature complete :: 3/14/2014 | ||
QA end to end test run 3/17/14 - 3/28/14 (sprint 4) | #Hard string Freeze :: 3/28/2014 | ||
Localization bug fixes complete 03/31/2014 – 04/21/2014 | #QA end to end test run :: 3/17/14 - 3/28/14 (sprint 4) | ||
Localization testrun 4/1/14 - 4/11/14 (sprint 5) | #Localization bug fixes complete :: 03/31/2014 – 04/21/2014 | ||
RTP - | #Localization testrun :: 4/1/14 - 4/11/14 (sprint 5) | ||
Feature list walk through 1.4 3/17/2014 | #RTP - Release to Partner :: 4/25/2014 | ||
Convergence branch creation 3/17/2014 | #Feature list walk through 1.4 :: 3/17/2014 | ||
Convergence done 4/25/2014 | #Convergence branch creation :: 3/17/2014 | ||
QC CS Currently 5/15 (will negotiate to 06/20/2014) | #Convergence done :: 4/25/2014 | ||
Regular blocker triage with RM 3/17/14 onwards | #QC CS :: Currently 5/15 (will negotiate to 06/20/2014) | ||
No more approvals on gaia flags 3/24/2014 | #Regular blocker triage with RM :: 3/17/14 onwards | ||
End to end regression 2: 4/15-14 - 4/25/14 (sprint 6) | #No more approvals on gaia flags :: 3/24/2014 | ||
End to end regression 3: post RTP -- on 1.4 branch | #End to end regression 2 :: 4/15-14 - 4/25/14 (sprint 6) | ||
Company Bug Bash week of 4/15/14 (sprint 6) | #End to end regression 3 :: post RTP -- on 1.4 branch | ||
Recommended IOT test start/ Customization testing complete 4/25/14 onwards | #Company Bug Bash :: week of 4/15/14 (sprint 6) | ||
#Recommended IOT test start/ Customization testing complete :: 4/25/14 onwards | |||
TA 11/20/2014 | #Recommended final IOT testing :: based on partner | ||
#TA :: 11/20/2014 |
Revision as of 00:14, 1 February 2014
1.4 Tracking
1.4 Schedule
- Milestones Schedule
- Sprint 1 – feature dev :: 2/3/14 – 2/14/14
- Sprint 2 – feature dev :: 2/17/14 – 2/28/14
- Sprint 3 – feature dev :: 3/3/14 – 3/14/14
- Sprint 4 – Planning (1.5) :: 3/17/14 – 3/28/14
- Sprint 4 - 1.4 stabilization begins
- Sprint 5 – stabilization :: 4/1/14 – 4/11/14
- Sprint 6 – stabilization :: 4/15/14 – 4/25/14
- Internal feature complete :: 3/14/2014
- Hard string Freeze :: 3/28/2014
- QA end to end test run :: 3/17/14 - 3/28/14 (sprint 4)
- Localization bug fixes complete :: 03/31/2014 – 04/21/2014
- Localization testrun :: 4/1/14 - 4/11/14 (sprint 5)
- RTP - Release to Partner :: 4/25/2014
- Feature list walk through 1.4 :: 3/17/2014
- Convergence branch creation :: 3/17/2014
- Convergence done :: 4/25/2014
- QC CS :: Currently 5/15 (will negotiate to 06/20/2014)
- Regular blocker triage with RM :: 3/17/14 onwards
- No more approvals on gaia flags :: 3/24/2014
- End to end regression 2 :: 4/15-14 - 4/25/14 (sprint 6)
- End to end regression 3 :: post RTP -- on 1.4 branch
- Company Bug Bash :: week of 4/15/14 (sprint 6)
- Recommended IOT test start/ Customization testing complete :: 4/25/14 onwards
- Recommended final IOT testing :: based on partner
- TA :: 11/20/2014