==Candice== | ==Candice== | ||
* In Taipei | * In Taipei | ||
==Chris Peterson (cpeterson)== | |||
* Hello! | |||
* Wrapping up some Q2 Android features | |||
* Geolocation meeting with potential partners | |||
==Dietrich== | ==Dietrich== | ||
Line 9: | Line 14: | ||
==Erin== | ==Erin== | ||
*Shipped Fx22 sans x86 which will follow later | |||
*Squeezed FHR into Fx23 Beta 1 | |||
*WebRT hack week last week to wrap on Q2 goals: we used Trello, https://trello.com/board/webrt-hack-week/51c8e4a4a3867d1a4b001295 | |||
*Focusing on WebRT, about:home, shumway, and lot's of other features on the roadmap | |||
*Ramping up more privacy and security technical reviews | |||
==Lawrence== | ==Lawrence== | ||
Line 19: | Line 29: | ||
==Marco== | ==Marco== | ||
* Metro team working on IT #10 from June 26, 2013 - July 11, 2013. | |||
* Q2 goals updated - working on Q3 goals list. | |||
* Assisting Martin on game related projects while he is away. | |||
==Sheila== | ==Sheila== | ||
==Tauni== | ==Tauni== | ||
* Management change in Identity Department | |||
** Ben's last day with Mozilla is Friday, July 5th | |||
** Lloyd Hilaiel is stepping up as the Director for the Identity Group | |||
* PiCL is focused on MVP to get a workable replacement for Sync in 2013 | |||
** What does this mean? | |||
*** A very clear focus on getting a workable solution in place for Desktop & Fennec (no new features) | |||
*** Working closely with both the Desktop/Fennec Development & Product staff |
Latest revision as of 17:19, 2 July 2013
Agenda
- Status/issues
Candice
- In Taipei
Chris Peterson (cpeterson)
- Hello!
- Wrapping up some Q2 Android features
- Geolocation meeting with potential partners
Dietrich
- In Taipei
Erin
- Shipped Fx22 sans x86 which will follow later
- Squeezed FHR into Fx23 Beta 1
- WebRT hack week last week to wrap on Q2 goals: we used Trello, https://trello.com/board/webrt-hack-week/51c8e4a4a3867d1a4b001295
- Focusing on WebRT, about:home, shumway, and lot's of other features on the roadmap
- Ramping up more privacy and security technical reviews
Lawrence
Martin
- In Europe
Michael
- In Taipei
Marco
- Metro team working on IT #10 from June 26, 2013 - July 11, 2013.
- Q2 goals updated - working on Q3 goals list.
- Assisting Martin on game related projects while he is away.
Sheila
Tauni
- Management change in Identity Department
- Ben's last day with Mozilla is Friday, July 5th
- Lloyd Hilaiel is stepping up as the Director for the Identity Group
- PiCL is focused on MVP to get a workable replacement for Sync in 2013
- What does this mean?
- A very clear focus on getting a workable solution in place for Desktop & Fennec (no new features)
- Working closely with both the Desktop/Fennec Development & Product staff
- What does this mean?