'''Status Key'''
{| class="wikitable"
! style="text-align: center;" | Color
! style="text-align: center;" | Status
! style="text-align: center;" | Key
|-
! style="background:#00EC00;" |
| On Target
| The project or deliverable is expected to meet its due date.
|-
! style="background:#FFFF00;" | 
| Challenged
| The project or deliverable is facing an issue that might cause it to miss its due date, but a “get well” plan has been developed to get it back on track.
|-
! style="background:#FF2800;" |
| At Risk or Late
| The project or deliverable is blocked or facing an issue that might cause it to miss its due date, and there’s no “get well” plan to get it back on track, or it is already late.
|-
! style="background:#00B2FF;" |
| Done
| The project or deliverable has been completed.
|-
! style="background:#C1C6CA;" |
| On Hold or Not Started
| The project or deliverable has either not been started or has been placed on hold.
|}
----
----