SmartPhone Code Transition: Difference between revisions

updated program status
(Renamed bug links to include the bug #)
(updated program status)
Line 230: Line 230:
! style="text-align: center;" | Status
! style="text-align: center;" | Status
! style="text-align: center;" | Status Notes
! style="text-align: center;" | Status Notes
|-
| Develop execution plan for the code transition
| 3/21/16
! style="background:#00EC00;" | On Target
| Meta bug created for the entire project. Next, need to identify milestones and target dates for tracking the progress of the work.
|-
|-
| Document requirements for build and test support for re-architecture effort.
| Document requirements for build and test support for re-architecture effort.
Line 243: Line 238:
| Set up branch, build, and test environment.
| Set up branch, build, and test environment.
| 3/18/16
| 3/18/16
! style="background:#FFFF00;" | Challenged
! style="background:#00B2FF;" | Done
| Created a meta-bug to track the build/test work here: https://bugzil.la/1252482. Working on some MarionetteJS enhancements to support the system app merge with TV.  B2G work is in Pine.  As expected, there is a lot of breakage to deal with.  We're able to produce builds, though.
| It's now possible to build B2G with the pine branch of Gecko and kanikani branch of Gaia.  
|-
|-
| Develop execution plan for the code transition
| 3/21/16
! style="background:#FF2800;" | Late
| Meta bug created for the entire project. Breakage is making it difficult to identify target dates for milestones.
|-
|-
| Code Transition Milestones
| Code Transition Milestones