Mobile/Firefox for Android/Sprint Status/Template: Difference between revisions
Line 5: | Line 5: | ||
*13 planned and 7 Resolved (53.85%); | *13 planned and 7 Resolved (53.85%); | ||
= Sprint# | = Sprint#7, 2017/May/1 ~ 2017/May/19 = | ||
== Sprint goal == | == Sprint goal == | ||
* | * Top line goals are LeanPlum integration and Photon Mobile. Most of the team will be in work week for Photon Mobile so we're extending the sprint duration to 3-week | ||
* | *Feature development on bookmark management keeps on-going targeting release 56 | ||
* | *P1 bug fixing for both PWA standalone mode and custom tab, targeting code complete by end of may to ride on release 55 | ||
* | *Finishing up the what's new page efforts for project dawn | ||
== Sprint# | == Sprint#7 backlog == | ||
<bugzilla> | <bugzilla> | ||
{ | { | ||
"id":[" | "id":["1329128", "1329131", "1329136", "1329130", "1357356", "1329152", "1361660", "1361664", "1361667", "1361670", "1367672", "1361673", "1357780"], | ||
"include_fields": "id, summary, status, resolution, assigned_to, whiteboard, last_change_time", | "include_fields": "id, summary, status, resolution, assigned_to, whiteboard, last_change_time", | ||
"order": "bug_id" | "order": "bug_id" |
Revision as of 03:24, 5 May 2017
Fennec Core Engineering Team Backlog
Review/Retro on previous sprint
Sprint#6 done.
- 13 planned and 7 Resolved (53.85%);
Sprint#7, 2017/May/1 ~ 2017/May/19
Sprint goal
- Top line goals are LeanPlum integration and Photon Mobile. Most of the team will be in work week for Photon Mobile so we're extending the sprint duration to 3-week
- Feature development on bookmark management keeps on-going targeting release 56
- P1 bug fixing for both PWA standalone mode and custom tab, targeting code complete by end of may to ride on release 55
- Finishing up the what's new page efforts for project dawn
Sprint#7 backlog
13 Total; 0 Open (0%); 11 Resolved (84.62%); 2 Verified (15.38%);
Project specific status
Custom tab
Overall project health
[GREEN, ON TRACK] 38 MVP bugs are planned; 20 Phase1 bugs, targeting firefox55 Phase1( April 17). QA has checked 25% of all bugs, bringing 13 more bugs for further clarification and follow-up. In total, we have 38 bugs for tracking, 21 out of these 38 bugs are resolved, representing a 95% phase1 completion rate, and 55% project completion rate, respectively.
Target Milestone
Firefox55
Project pages (if any)
- Custom Tab Project Mana Page : CustomTab Project Mana Page
- Custom Tab Project Wiki Page : CustomTab Project Wiki Page
Bookmark management
[GREEN, ON TRACK] Engineering team work on bugs.
- Bug 1329127 - [META] Fennec Bookmark Management
General (triage)
[GREEN, ON TRACK] We keep backlog grooming for the long list
Fennec Feature backlog
[GREEN, ON TRACK] [Bug 1341545] [meta] Fennec Feature backlog collection
UX polish
[GREEN, ON TRACK]
- Bug 1157964 - (fennec-polish) [meta] Fennec UX polish
UX had finished input and we had prioritization into the backlog. We're still continuing taking new suggestions when it comes to user experience improvements.
Performance dashboard
[GREEN, ON TRACK] Currently running manual initial benchmark perf testing and study tooling.
- Bug 1320263 - Feasibility/PoC for Fennec performance assessment
RTL
Overall project health
[GREEN, ON TRACK, ready in Firefox53] QA has checked 100% of all bugs, bringing 16 more bugs for further clarification and follow-up.
In total, we have 29 bugs for tracking, 24 out of these 29 bugs are resolved, representing a 83% completion rate. l10n team included 4 RTL locals( Hebrew, Arabic, Urdu, Persian ) into the multilocales build of firefox53.
Target Milestone
Firefox53
Project pages (if any)
- RTL Project Wiki Page : RTL Project Wiki Page