Line 77: |
Line 77: |
| |- | | |- |
| | 2 | | | 2 |
| | Late definition and completion of v1 features for identity and payments flow delays formal definition and execution of testing
| |
| | Dependencies for feature complete definition and completion are missing target dates
| |
| | N/A, since we're past the target date already
| |
| | Finalize the v1 payments and identity user stories, identify gaps in the implementation, and fix those gaps
| |
| |-
| |
| | 3
| |
| | Resource unavailability during the Holiday season | | | Resource unavailability during the Holiday season |
| | Developers, Testers and Product resources being on PTO around the Holiday season. | | | Developers, Testers and Product resources being on PTO around the Holiday season. |