Connected Devices Weekly Update/2016-10-20: Difference between revisions
Jump to navigation
Jump to search
No edit summary |
No edit summary |
||
Line 23: | Line 23: | ||
* Continuation of weekly 3rd party vendor meetings to support creation of early Sensor hardware development boards by end of Dec 2016. | * Continuation of weekly 3rd party vendor meetings to support creation of early Sensor hardware development boards by end of Dec 2016. | ||
** Upcoming Milestone: Firm Key components list and detail Hardware Development Schedule with task and ownership for Dec 2016 | ** Upcoming Milestone: Firm Key components list and detail Hardware Development Schedule with task and ownership for Dec 2016 | ||
|- | |||
| [[Connected_Devices/Projects/Project_Haiku|Project_Haiku (taking in Project Smart Display)]] | | [[Connected_Devices/Projects/Project_Haiku|Project_Haiku (taking in Project Smart Display)]] | ||
| Liz/Joe/Mahe | | Liz/Joe/Mahe |
Revision as of 16:17, 20 October 2016
<< Connected Devices Weekly Updates Home
Program | Passed Gate | Status | Notes | |
---|---|---|---|---|
Project Sensor Web | Cindy/Jean | Gate 1 | On Target |
|
Project_Haiku (taking in Project Smart Display) | Liz/Joe/Mahe | Gate 0 | On Target |
|
Platform and Tools | Sandip/Nicole/Mahe | N/A | On Target |
|
Voice Platform - Deep Speech | Sandip/Nicole | N/A | On Target |
|
Abigail | Preeti/Julie | Gate 0 | On Target |
Prototype Development and Testing
Work Week Update
Schedule
|
Project Magnet | David/Maria | Gate 0 | On Target |
|
HomeWeb | Ben/Mahe | Gate 0 | On Target |
|
GameON! | Candice/Julie | Pre Gate 0 | On Target |
Product Definition
Engineering
|
Lighthouse | Preeti/Julie | Gate 0 | On Target |
Engineering
User Study with Prototype
Schedule
|
PocketID | Francisco | Pre Gate 0 | On Target |
|
3D Printing | Thomas | Pre Gate 0 | On Target |
|
Participation Update | Michael/Brian | -- | On Target |
|
Market Developments Update | Irina |
| ||
Other Announcements / Questions | -- | -- |