Mobile/Firefox for Android/Sprint Status/2017 Sprint5: Difference between revisions
(Created page with "= Fennec Core Engineering Team Backlog = [https://trello.com/b/dqy3uDRv/fennec-core-engineering Fennec Core Eng Trello] = Review/Retro on previous sprint = [https://wiki.mozil...") |
|||
Line 2: | Line 2: | ||
[https://trello.com/b/dqy3uDRv/fennec-core-engineering Fennec Core Eng Trello] | [https://trello.com/b/dqy3uDRv/fennec-core-engineering Fennec Core Eng Trello] | ||
= Review/Retro on previous sprint = | = Review/Retro on previous sprint = | ||
[https://wiki.mozilla.org/Mobile/Firefox_for_Android/Sprint_Status/ | [https://wiki.mozilla.org/Mobile/Firefox_for_Android/Sprint_Status/2017_Sprint4 Sprint#4 ]done. | ||
14 Total; 10 Open (71.43%); 4 Resolved (28.57%); | |||
From the completion is looks bad but the 10 open bugs all have patches in review process. | |||
Next sprint we will do a 4-week period considering the upcoming holidays and PTO. | |||
= Sprint#2, 2017/Jan/23 ~ 2017/Feb/17 = | = Sprint#2, 2017/Jan/23 ~ 2017/Feb/17 = | ||
== Sprint goal == | == Sprint goal == |
Revision as of 10:24, 20 March 2017
Fennec Core Engineering Team Backlog
Review/Retro on previous sprint
Sprint#4 done. 14 Total; 10 Open (71.43%); 4 Resolved (28.57%); From the completion is looks bad but the 10 open bugs all have patches in review process. Next sprint we will do a 4-week period considering the upcoming holidays and PTO.
Sprint#2, 2017/Jan/23 ~ 2017/Feb/17
Sprint goal
- RTL Refinement targeting Firefox54?
- Start the engineering task of Custom tab targeting FirefoxXXXX ?
Sprint backlog
14 Total; 0 Open (0%); 3 Resolved (21.43%); 11 Verified (78.57%);
Project specific status
RTL
Overall project health
[GREEN, ON TRACK] QA has checked 89% of all bugs, bringing 6 more bugs for further clarification and follow-up.
In total, we have 15 bugs for tracking, 4 out of these 15 bugs are resolved, representing a 27% completion rate.
Target Milestone
Firefox53
Project pages (if any)
- RTL Project Wiki Page : RTL Project Wiki Page
General (triage)
[GREEN, ON TRACK] We keep backlog grooming for the long list
UX polish
[GREEN, ON TRACK]
- Bug 1157964 - (fennec-polish) [meta] Fennec UX polish
UX had finished input and we had prioritization into the backlog. We're still continuing taking new suggestions when it comes to user experience improvements.
Performance dashboard
[GREEN, ON TRACK] Currently running manual initial benchmark perf testing and study tooling.
- Bug 1320263 - Feasibility/PoC for Fennec performance assessment
Bookmark management
[GREEN, ON TRACK] User stories initiated. Currently in UX design phase.
- Bug 1329127 - [META] Fennec Bookmark Management
Custom tab
[GREEN, ON TRACK] User stories initiated. Currently in UX design phase.
- Bug 1208655 - (customtabs) [meta] Make Fennec be an Android "custom tab" ecosystem participant