Line 35: | Line 35: | ||
==Ops (Owner: mrz)== | ==Ops (Owner: mrz)== | ||
* Make load test work | * Make load test work - DONE | ||
** Augment frontend network infrastructure (05/21) | ** Augment frontend network infrastructure (05/21) | ||
** Replace HDDs in LDAP slaves with SSDs (05/21) | ** Replace HDDs in LDAP slaves with SSDs (05/21) | ||
Line 45: | Line 45: | ||
* Get ops playbook done | * Get ops playbook done | ||
** perpetual work in progress | ** perpetual work in progress | ||
* Lock down iptables/fw rules | * Lock down iptables/fw rules [5/23] | ||
** Zeus | ** Zeus | ||
==Security (Owner: Clyon)== | ==Security (Owner: Clyon)== | ||
Line 59: | Line 59: | ||
==Marketing (Owner: Mayumi)== | ==Marketing (Owner: Mayumi)== | ||
* Blog post ready | * Blog post ready - DONE | ||
* Web pages ready | * Web pages ready [5/21] | ||
==Support (Owner: Ragavan/Tenser)== | ==Support (Owner: Ragavan/Tenser)== | ||
Line 67: | Line 67: | ||
==Metrics (Owner: Ken)== | ==Metrics (Owner: Ken)== | ||
* Make sure metrics are in place and ready to point at the new environment | * Make sure metrics are in place and ready to point at the new environment | ||
** We are in good shape -- it doesn't look like we need to do any major refactoring, IT should be able to deploy the kit we provided to staging to test with. | ** We are in good shape -- it doesn't look like we need to do any major refactoring, IT should be able to deploy the kit we provided to staging to test with. [5/23] |
Revision as of 21:11, 21 May 2010
Server Engineering (Owner: Toby)
- Tag and deploy a stable version of code - DONE
- Done. 1.3 tagged for sync, registration and registration-secure
- Enable mx scripts
- Documentation [5/20] DONE
- Scripts have been rewritten to work with cleaner config. Need multiple-node setup to test on. [5/21] ONTRACK
- At this point, it becomes an operations issue.
- Test migration [5/24]
- Need firewall holes and somewhere to deploy it. [5/21]
- Migration plan at https://intranet.mozilla.org/Labs/Weave/MigrationPlan
Client Engineering (Owner: MConnor)
Key Links:
l10n dashboard services.m.c stage
Add-on:
- b6 release [5/21]
- string frozen, tagged in both repos (weave + en-US)
- includes all green locales from l10n
- pointing at final URLs
- RC1 release [5/24]
- All locales showing green as of 8 AM PDT Monday will be included in this build.
- Spin final release build (late Monday/early Tuesday) [5/25]
- stage to AMO once we have a go (Tuesday AM?)
Web stuff:
- services.mozilla.com [5/21]
- get updated privacy policy/Terms of Service docs from legal and into SVN [5/21]
- provide links on mozillalabs.com to new URLs - [5/21]
- rebranding done and all content in place - [5/21]
Ops (Owner: mrz)
- Make load test work - DONE
- Augment frontend network infrastructure (05/21)
- Replace HDDs in LDAP slaves with SSDs (05/21)
- Get monitoring in place (05/24)
- wp-zlb (Zeus) in Nagios bug 565926
- LDAP replication lag bug 565946
- Get trending in place (05/24)
- LDAP replication
- Get ops playbook done
- perpetual work in progress
- Lock down iptables/fw rules [5/23]
- Zeus
Security (Owner: Clyon)
- Verify logging in production (once load testing is completed 5/21) [bug 567436]
- Verify security event rules are firing (5/21 once logging is completed)
- Final infrastructure review (5/24 to be completed by, will start 5/21)
QA (Owner: TChung)
- Complete utest (eta Monday 5/24) see matts email
- QA will resume testing beta 6 when available, and run through smoketests and bfts. ETA to run those without hiccups is 2-4 hours. This will be against production server (includes fennec)
- update: beta 6 landed 5/21, so targeting signoff on 5/24.
Marketing (Owner: Mayumi)
- Blog post ready - DONE
- Web pages ready [5/21]
Support (Owner: Ragavan/Tenser)
- Make sure support KBs are reviewed and ready to go. (ETA: Friday, May 21)
Metrics (Owner: Ken)
- Make sure metrics are in place and ready to point at the new environment
- We are in good shape -- it doesn't look like we need to do any major refactoring, IT should be able to deploy the kit we provided to staging to test with. [5/23]