==Timeline to implementation== | ==Timeline to implementation== | ||
Identify the length time we have to incorporate your project into the overall workflow, including noteworthy milestones. For an example of what we're looking for, see the [https://docs.google.com/spreadsheet/ccc?key=0Al5H7QuXOsNZdGh0LXRQWlB6OTZGa2kzV2loRXpFT3c&hl=en_US|Live#gid=0 Firefox Live timeline]. | Identify the length time we have to incorporate your project into the overall workflow, including noteworthy milestones. For an example of what we're looking for, see the [https://docs.google.com/spreadsheet/ccc?key=0Al5H7QuXOsNZdGh0LXRQWlB6OTZGa2kzV2loRXpFT3c&hl=en_US|Live#gid=0 Firefox Live timeline]. | ||
Briefing the localization team about the localization procedures - by March 15 | |||
Distributing the tasks - by March 16 | |||
Feedback and Q&As - by March 20 | |||
Front end localization - by May 1 | |||
Testing - by May 10 | |||
Back end localization - by June 1 | |||
Testing - by June 10 | |||
Going live - by June 15 | |||