==1.4 Tracking==
==1.4 Tracking==
==1.4 Schedule==
==1.4 Schedule==
* Milestones Schedule
** Sprint 1 – feature dev 2/3/14 – 2/14/14
** Sprint 2 – feature dev 2/17/14 – 2/28/14
** Sprint 3 – feature dev 3/3/14 – 3/14/14
** Sprint 4 – Planning (1.5) 3/17/14 – 3/28/14
** Sprint 5 – stabilization 4/1/14 – 4/11/14
** Sprint 6 – stabilization 4/15/14 – 4/25/14
** Internal feature complete 3/14/2014
Hard string Freeze 3/28/2014
QA end to end test run 3/17/14 - 3/28/14 (sprint 4)
Localization bug fixes complete 03/31/2014 – 04/21/2014
Localization testrun 4/1/14 - 4/11/14 (sprint 5)
RTP - release to partner 4/25/2014
Feature list walk through 1.4 3/17/2014
Convergence branch creation 3/17/2014
Convergence done 4/25/2014
QC CS Currently 5/15 (will negotiate to 06/20/2014)
Regular blocker triage with RM 3/17/14 onwards
No more approvals on gaia flags 3/24/2014
End to end regression 2: 4/15-14 - 4/25/14 (sprint 6)
End to end regression 3: post RTP -- on 1.4 branch
Company Bug Bash week of 4/15/14 (sprint 6)
Recommended IOT test start/ Customization testing complete 4/25/14 onwards
Recommded final IOT testing based on partner
TA 11/20/2014

Revision as of 00:04, 1 February 2014

1.4 Tracking

1.4 Schedule

  • Milestones Schedule
    • Sprint 1 – feature dev 2/3/14 – 2/14/14
    • Sprint 2 – feature dev 2/17/14 – 2/28/14
    • Sprint 3 – feature dev 3/3/14 – 3/14/14
    • Sprint 4 – Planning (1.5) 3/17/14 – 3/28/14
    • Sprint 5 – stabilization 4/1/14 – 4/11/14
    • Sprint 6 – stabilization 4/15/14 – 4/25/14
    • Internal feature complete 3/14/2014

Hard string Freeze 3/28/2014 QA end to end test run 3/17/14 - 3/28/14 (sprint 4) Localization bug fixes complete 03/31/2014 – 04/21/2014 Localization testrun 4/1/14 - 4/11/14 (sprint 5) RTP - release to partner 4/25/2014 Feature list walk through 1.4 3/17/2014 Convergence branch creation 3/17/2014 Convergence done 4/25/2014 QC CS Currently 5/15 (will negotiate to 06/20/2014) Regular blocker triage with RM 3/17/14 onwards No more approvals on gaia flags 3/24/2014 End to end regression 2: 4/15-14 - 4/25/14 (sprint 6) End to end regression 3: post RTP -- on 1.4 branch Company Bug Bash week of 4/15/14 (sprint 6) Recommended IOT test start/ Customization testing complete 4/25/14 onwards Recommded final IOT testing based on partner TA 11/20/2014