* {{ok |Ensure 1.4 is on-track to be delivered with high quality}}  [bajaj]
* {{ok |Ensure 1.4 is on-track to be delivered with high quality}}  [bajaj]
* {{ok |Run dogfooding program once the reference device is delivered}}  [Preeti]
* {{ok |Run dogfooding program once the reference device is delivered}}  [Preeti]
** Work done so far:
*** Initial investigation on the device itself
*** Understand update policy and what was needed for Phase 1
*** CURRENT STATUS: Awaiting reference phone

Revision as of 15:06, 24 March 2014

General Engineering

  • Become more involved in the community
    • [ON TRACK] Each RM should write blog (or dev.planning) posts explaining/proposing RM processes and improvements
      • [bajaj] Experience on working with Community Release Managers and bringing them upto speed, Metro Release
      • [lsblakk] Revised Coupled Train Model, Update on comm release managers wrt tracking volume and effectiveness, Work Week blog posts
      • [preeti] Current issues with B2G, How is Release Management at Mozilla different from Juniper Networks
        • DONE
      • [sylvestre] joining Mozilla
      • [willie]
      • [alco]
      • [bkerensa]
  • Continue our tools & automation work
    • [ON TRACK] Deliver a Release Readiness Dashboard [bajaj, willie]
    • [ON TRACK] Round 3 of the triage dashboard
      • [lsblakk] continue improvements to allow for use by wider audience (managers, devs) - public 'release' but still on staging env at first
        • move off personal server to PAaS deploy
        • custom view default per org chart (target audience: eng. mgr)
    • Bug fixes and ESR support to merge-helper scripts
    • Round 2 on auto-updating product-details (we're still a quarter out from no longer needing to edit)


  • Work Week Planning for 2014
    • [ON TRACK] Complete separation of focus between desktop/mobile and OS [bajaj]

Firefox Desktop/Mobile

  • [ON TRACK] Continue working on implementing a Coupled Train Model, blog post and discussion about the new plan (with no affect to l10n this time) goal is to finalize a plan of action to start in Q2 [lsblakk]
  • [MISSED] Work with Devs, PM team, Marketing/PR, and others to draft a proposal for a revamped Aurora -- this will go to a later quarter, after coupled train [sylvestre, lsblakk]
  • [ON TRACK] Help deliver Metro Release, current target is Firefox 28, hand off into trains [bajaj]

Firefox OS

  • [ON TRACK] Ensure 1.4 is on-track to be delivered with high quality [bajaj]
  • [ON TRACK] Run dogfooding program once the reference device is delivered [Preeti]
    • Work done so far:
      • Initial investigation on the device itself
      • Understand update policy and what was needed for Phase 1
      • CURRENT STATUS: Awaiting reference phone