Program Passed Gate Status Notes
Project Sensor Web David/Julie Gate 1 Delayed

Revised SensorWeb Timeline

SensorWeb Timeline Jan 26.png

  • Building test units of the SensorWeb device and the manufacture of those devices have been delayed, pending a final budget decision. The overall project timeline has been adjusted accordingly. At this point, we're running about 5 weeks behind the original schedule.

Beta Service and Developer Offering

  • Team is working on the deliverables for the beta service and developer offering.
  • Sprint 6, ending January 26th, has been focused on Favorites and the behavior when launching the the app (mobile and website) and authentication.
  • Upcoming sprints will focus on developer access.

SensorWeb SDK

  • A SensorThings SDK for developers consisting of Web Service endpoints, documentation for SensorWeb, example code, and release notes for developer who wish to have early access to SensorWeb web services. Additionally, we will add access control to our SensorWeb Cloud service through client and user authentication. We will have this available as a closed beta to developers who wish to have early access. Included in this release is API authentication.
  • This release will be an “early release”, not intended for large scale commercial deployment. It sets a foundation for further development. The objectives are:
    • Engage developers in the community to use the SensorWeb platform
    • Test our SensorWeb API for usability, reliability and completeness for both custom-defined Things (devices) and Perch (our) devices and solicit feedback via closed beta for the SDK
  • Demonstrate an early consumer-facing service offering utilizing PM2.5, temperature and humidity data in a visualization
  • Give developers (contributors) the ability to add /remove/modify devices that they own
  • Enable developers to add devices compatible with our SensorWeb Device

SensorWeb Device

  • As a reminder, the SensorWeb device has not yet been manufactured. About 25 early boards have been produced and distributed to internal members of the SensorWeb project team for testing and development purposes.

SensorWeb Develop Board V1.3.png

Platform and Tools Sandip/Mahe N/A On Target
  • Bulleted list item
  • Bulleted list item
Project Magnet Wilson/Maria Gate 1 Delayed
  • Release of the Magnet application at the end of Q1 has been delayed since we are waiting for key resources as the Visual Design and the Content Curator.
  • This week will finish the first version of the Wireframes, that is being reviewed by all the team and during the following two weeks, Francis will create a version of the application in Invision (mockup) that will be used for a Usability Test
  • The Usability Test is planned to be done in Vancouver with fewer number of participants and Mihalea's offered to do the recruitment herself. Early feedback will give us more time to guide the visual design.
  • Sprint 11 (January 23th - Feb 3rd) started this week
    • Last sprint (Sprint 10) we worked hard on the React components, so we are in good shape to finish them this week. We finished the App Navigation and Deep linking tasks but we couldn't move too far in the Backend part.
    • During this sprint 11, we are not going to have visuals yet, we need to do all the work that doesn't require UI: Finishing all the React Components and all the backend part including the libraries and API.

Updated Time plan Jan26 updated Magnet timeline.png

Milestones

  • UX Wireframes (first Iteration): 27/01/2017
  • Usability Testing: 24/02/2017
  • Visual Design of the app finished: Planned on 24/02/2017 -> Delayed 3-4 weeks
  • Street Art content included in the Metadata Server: March 31
  • Beta version of the application ready in the stores: Planned on March 31 -> Delayed 3-4 weeks
  • Marketing campaign launched: planned during April 2017 -> Delayed 3-4 weeks
Lighthouse Preeti/Julie Gate 1 Delayed

Sprint 2 (January 18-31) Resourcing

  • Pending resource funding decisions are a risk the overall schedule. QA assistance and a visual designer are needed to finish up the app.
  • Backup plan is for project team members to do QA testing. Team has also discussed using community help for QA and engagement of members of the accessibility community.
  • Team will also reach out to visual designers within Mozilla who are outside of CD.
  • Also wanted to start some work on the hardware side, but need industrial design help for that. This is currently on hold, pending the funding decision. We won’t be able to make our Q1 goal around ID.

App Progress

  • Planning and design work was conducted this week for the app.
  • Focus has been on diagramming the desired user interactions, with lots of collaboration within the team taking place.
  • Work is continuing on image capture and matching as well.
    • Activities around getting app into TestFlight
    • Identification of marketing channel(s)
    • Product description
    • Channel identification - created a list of Blind Center Contacts in California/other locations
  • Held Legal Review and identified deliverables (hold review of app, write terms, privacy notice)

Planning

  • Will hold more formal planning sessions next week to build out a more complete plan and schedule
Participation Update Michael/Brian N/A On Target
  • Bulleted list item
  • Bulleted list item
Market Developments Update Irina N/A
  • Bulleted list item
  • Bulleted list item
Other Announcements / Questions N/A