====Metro Highlights====
<p> </p>
* Iteration #6: [https://bugzilla.mozilla.org/show_bug.cgi?id=855905 April 17, 2013 - April 30, 2013]
<p> </p>
* Highlights
** Team completed '''75 story points''' across '''25 features''' at the conclusion of Iteration #5 - a '''19% increase in performance''' from the previous iteration.
** Team has established a new average velocity rate of '''47 story points per iteration''' at the conclusion of Iteration #5 - a '''17% increase in performance''' from the previous iteration.
** Overall performance gain in story points and velocity at the conclusion of Iteration #5 has resulted in a new production forecast release of '''December 23, 2013''' - a '''reduction of 3 iterations''' from the previous release update.
** Product Manager review of V1 Release List resulted in the removal of '''9 Feature Stories to V2.'''
** At the conclusion of Iteration #6 the project will have acquired enough data to present three release forecast scenarios:  Worst, Expected and Best case.
<p> </p>
====Iteration Performance Summary====
<p> </p>
* Total Work:  '''109 total story points - 27 bugs.'''
** '''16''' feature stories.
** '''9''' defect stories.
** '''2''' change stories.
<p> </p>
* Completed Work: '''27 story points closed - 15 bugs - 24% complete.'''
** '''7''' feature stories.
** '''7''' defect stories.
** '''1''' change story.
<p> </p>
* Remaining Work: '''82 story points closed - 12 bugs - 76% complete.'''
** '''9''' feature stories.
** '''2''' defect stories.
** '''1''' change story.
<p> </p>
====Iteration Work Details====
<p> </p>
<bugzilla>
    {
        "id": "831916, 831918, 831934, 833133, 833182, 835623, 838497, 849395, 850737, 851900, 852090, 855578, 862054, 831894, 831919, 833130, 833131, 833132, 833200, 852805, 854070, 854077, 855581, 855587, 859447, 860994, 862025, 863060"
    }
</bugzilla>
<p> </p>


==Sheila==
==Sheila==
Confirmed users
4,160

edits