Status Report for Example Project for the week/period of dd/mm/yy - dd/mm/yy

Overall Project Health

This Week Last Week

 

 

Exec Summary/Hot Topics

  • A new 'go to market' date has not yet been established for V1. Working toward resolving this at mozwww.
  • Testflight was expanded to included nearly 350 new external testers this week.
  • Product is very near to 'feature complete' for V1 planned scope, but much work is still ongoing around fixes and improvements based on testing and feedback


Risks & Issues

Description of Risk/Issue State Owner Plan to Resolve/Mitigation Target Date
A new launch date for the V1 Firefox on iOS product has not been established since removing it from the scope of the June 2nd campaign. Open Jenn A goal has been established for mozwww to work on the end game plan with milestone dates June 29th

Accomplished for the Last Period

  • Landed Feature A
  • Made Decision B
  • Finalized Plan C

Planned for Last Period but Not Accomplished

  • Did not land feature D as planned
  • Decision E still under discussion

Planned for the Upcoming Period

  • Land feature D
  • Finalize decision E
  • Land feature F

Status Details

Important Links/References