Connected Devices Weekly Update/2016-10-20

From MozillaWiki
Revision as of 16:53, 20 October 2016 by Mpotharaju (talk | contribs)
Jump to navigation Jump to search

<< Connected Devices Weekly Updates Home

Program Passed Gate Status Notes
Project Sensor Web Cindy/Jean Gate 1 On Target
  • PIB Checkin this Fri, Oct 21 to provide follow up action items from Oct 4 Gate1 review:
    • Provide details project plan on 4 main components: Cloud/API, Updates, Device and Hardware.
    • Provide updated Architecture diagrams
    • Provide next level budget forecast to 2017
    • Provide detail AWS data hosting costs
  • SensorWeb Branding
    • Checkin meeting with Branding team Oct 26th to review proposed branding framework
  • Kicked off User study #1 for user interviews in Taipei to start Oct 25 to 28.
    • This study will cover UI/ID and installation, unboxing experience, user interaction of setup process and value proposition.
  • Continuation of weekly 3rd party vendor meetings to support creation of early Sensor hardware development boards by end of Dec 2016.
    • Upcoming Milestone: Confirmed key components list and detail Hardware Development Schedule with task and ownership for Dec 2016
Project_Haiku (taking in Project Smart Display) Liz/Joe/Mahe Gate 0 On Target
  • UR 9 Wrapped. Prototypes in return shipping
    • UR 9 surveys completed. Being synthesized into a report
    • UR 9 usage data report here
    • UR 9 detailed report by next week
Platform and Tools Sandip/Nicole/Mahe N/A On Target
  • Bulleted list item
  • Bulleted list item
Voice Platform - Deep Speech Sandip/Nicole N/A On Target
  • Integration of Fisher+Switchboard Corpus in Deep Speech
  • Creating English Language Model
    • Created English corpus from Wikipedia
    • Starting on creation of a RNN (how the machine learns) language model
  • Create demo milestones for Hawaii
    • Demo Ideas:
      • Talking santa
      • WER chart
      • Browser add-on that has basic control of browser
      • Robot - grammar
      • Live transcription demo
      • Integrate decoder with web speech API on firefox browser--gecko
      • webvr and aframe demos with speech
  • Hosting of WER chart http://doyouunderstand.me/


Screen Shot 2016-10-20 at 9.44.32 AM.png

Abigail Preeti/Julie Gate 0 On Target

Prototype Development and Testing

  • Continued work to test value propositions.
    • Finalizing a questionnaire and visual designs to use in a study next week with targeted market segment to test value props. Targeting Oct. 24th to launch this study.
    • Developing ad copy for a campaign to drive traffic to a landing page
    • Finalizing copy for landing page that will feature a video.
    • Writing script for the video that will describe the overall purpose and functionality of Abigail to get consumer feedback. Feedback from the study will be incorporated into the video.
  • Reviewed first drafts of industrial design proposals. Feedback is being incorporated into the second drafts which will be reviewed today (Oct. 20).

Work Week Update

  • Completing work for end-to-end integration for reminder use-case.
    • Further work breakdown was completed on the first day.
    • Good progress is being made and work is on track for on time completion.

Schedule

  • Value proposition validation - Oct. 24 - early November
  • Prototype development: month of October
  • Assembly of devices: week of October 31
  • Testing in homes: November 7 - 18
  • Data synthesis from pilot and video/landing page studies: November 21 - 29
  • Gate 1 pitch: November 30
Project Magnet David/Maria Gate 0 On Target
  • Finishing our first Sprint (Sprint 6) after passing Gate 0 (more details of the sprint in our Waffle and our wiki). Main Goal for this sprint is implementing our current service/client to work for GPS/Virtual beacons
    • Architecture

Magnet Client Flow Virtual Beacons v2.png

  • Main Tasks:
    • Investigate and implement GPS solutions in React Native (iOS and Android)
      • Implement GPS content discovery on client
      • Geo Backend: Implement Magnet Service
    • Upgrade to latest react-native version as there were errors when compiling magnet for iOS10 and bugfixing
    • Metrics: Modify the metrics to identify Beacons URL and GPS or Virtual Beacons
    • Provide content for the London Pilot that fit our target audience and our technical requirements
    • Design of several options for the final UX of our client (High level)
  • Working in the presentation for the PIB (Oct 21st) to nail down the target audience and stories for our Pilot/MVP
HomeWeb Ben/Mahe Gate 0 On Target
  • Team assigned (mostly)
  • Order placed for hardware evaluation kits, waiting for delivery (Engineers ramping up on research while we wait)
  • Several team members meeting with hardware vendor at IoT Expo on Friday
  • Setting up landing page & survey tools
  • Started mocking up landing page & survey, will engage UR/UX/Marketing for input
GameON! Candice/Julie Pre Gate 0 On Target

Product Definition

  • Focus is on product differentiation and tech enhancements that will bring something totally new with this concept
  • Use case refinement has narrowed the scope of a first iteration prototype that will be proposed in Gate 0 pitch
  • Refining the Gate 0 pitch and will send it out for feedback in the coming week
  • Gate 1 pitch: November 30

Engineering

  • Development of a game board simulator and also a physical board with an LED base

Game board prototype.png

  • Evaluating Hall sensors and magnets
    • Prototype spinner developed

Kevin's spinner.png

  • Identified specific requirements around basic game play
  • Working on a demo for the Gate 0 Pitch presentation
Lighthouse Preeti/Julie Gate 0 On Target

Engineering

  • Work on image matching is progressing well. Might work well enough to not have to worry about separating out background during image acquisition
  • Testing alternatives for mic/speaker, including Wolfson card, Wilson card that uses I2S expansion bus on rpi, as well as USB option. Goal is to make a quick decision so that prototype can be assembled in time for the study.
  • Team is looking for an additional engineer to help on this project

User Study with Prototype

  • Testing hypotheses around technical feasibility, that study participants will trust it, not the testing of specific form factors.
  • Current thinking is that team members will accompany participants on shopping outings and possibly assist in taking photos of the items being purchased, as the focus of the study is on how well image matching works, not on how easy it is for the participants to take the photos.

Schedule

  • Complete development of prototype: October
  • Assemble prototypes: Oct 31 - Nov 4
  • Prototype pilot: Nov 7 - 18
  • Data synthesis from pilot and video/landing page studies: November 21 - 29
  • Gate 1 pitch: November 30
PocketID Francisco Pre Gate 0 On Hold
  • Hard dates for project Magnet and project Sensor Web, so the team cannot continue working on PocketID after December
3D Printing Thomas Pre Gate 0 On Target
  • Bulleted list item
  • Bulleted list item
Market Developments Update Irina
  • Bulleted list item
  • Bulleted list item
Other Announcements / Questions -- --