Firefox Activity Stream Program - Cross-Platform Status Report - Apr-04-2017

Overall Project Health

  On track, issues well managed   Some risks, unknowns without clear mitigations   Blocked on deliverables, needs decision, escalation required

Platform/Area Version Health Notes
Desktop FF57

 

MVP feature development progressing well. 'Wapusk' sprint was kicked off Apr 3rd, ending Apr 16th. Revised Graduation work broken down, and new schedule generated, targeting FF57.
Android FF??

 

Sprint 1.19 (ending Apr 16) has been kicked off. Team capacity still impacted by ~66% as resources temporarily assigned to another higher priority initiative (Focus Android). Schedule will be re-baselined once all resources are back on board, which should be late April.
iOS V8.0

 

Sprint 1.19 (ending Apr 16) has been kicked off; V8.0 now in stabilization. MVP feature development on track for V8.0, and the outstanding MVP bug list tracking 8.0 is getting very short.

Exec Summary/Hot Topics

Desktop

  • Current Sprint 'Wapusk
  • Graduation plans have been finalized and work breakdown completed. A new schedule baseline has been generated to accout for the additional work, and is now tracking to land in FF57.

Android

  • Current Sprint 1.19
  • Continuing on with remaining MVP feature development. MVP Backlog can be found here.
  • Schedule will need to re-baselined once all resources are back in place. 2/3 of team has been reassigned temporarily to another high-priority initiative (Focus for Android). Currently anticipate having the team back at full strength in late April, at which point a new schedule will be communicated.

iOS

  • Current Sprint 1.19
  • Continuing on with remaining MVP feature development. MVP Backlog can be found here.
  • MVP Development on track for V8.0. The MVP backlog of tracking bugs is getting very small!

Risks & Issues

Description of Risk/Issue Affected Platform(s) State Owner Version Plan to Resolve/Mitigation Target Date
Android AS resource availability Android Open Eng 2/3 Android resources temporarily reassigned. Apr 30

Development Status

  On track, issues well managed   Some risks, unknowns without clear mitigations   Blocked on deliverables, needs decision, escalation required