December 2008

  • Dec. 5: Mary to hand off final files (done)
  • Dec. 31: Neil to splice PSDs and create CSS/HTML (moved to Jan)

January 2009

Redesign:

  • Jan. 12th: Neil to splice PSDs and create CSS/HTML
  • Jan. 26th: CSS/HTML implemented in SFX codebase/site staged
  • Jan. 28th: Marketing to provide feedback
  • Jan. 30th: Alex to complete P1 admin needs for new SFx

Drupal Migration:

  • Jan. 9th:
    • Alex to file a bug to get a staging server up
  • Jan. 16th:
    • Mary, Paul and team to resolve Varbinary issue
    • Alex to get staging server set up (is this an IT issue?)
  • Jan. 19th: Get Sfx database copied over (is this still needed?)

February 2009

Redesign:

  • Feb. 4th: Site iterations complete

Drupal Migration:

  • Feb. 9th: Finish new theme

March 2009

  • March 2nd: Site QA kicks off
  • March 23rd: New site live
  • Feb. 16th: Site live