CloudServices/Sync/FxSync/Archived/13GoLive

From MozillaWiki
Jump to navigation Jump to search

Server Engineering (Owner: Toby)

  • Tag and deploy a stable version of code
  • Enable mx scripts
  • Test migration

Client Engineering (Owner: MConnor)

  • Send out hard cut on localization
  • Finish web content and make sure it's staged

Ops (Owner: MRZ)

  • Make load test work
    • Augment frontend network infrastructure (05/21)
    • Replace HDDs in LDAP slaves with SSDs (05/21)
  • Get monitoring in place
  • Get trending in place
    • LDAP replication
  • Get ops playbook done
  • Lock down iptables/fw rules
    • Zeus (05/20)
    • Infra Sec. review

Security (Owner: Clyon)

  • Verify logging in production (once load testing is completed 5/21)
  • Verify security event rules are firing (5/21 once logging is completed)
  • Final infrastructure review (5/21 and into the weekend)

QA (Owner: TChung)

  • Complete utest
  • Finish all other testing and sign off (qa, fill in here as needed)
    • Smoketest+ beta6 build when available (completion - 1-2 days after build eta)

Marketing (Owner: Mayumi)

  • Blog post ready
  • Web pages ready

Support (Owner: Ragavan/Tenser)

  • Make sure support KBs are reviewed and ready to go. (ETA: Friday, May 21)

Metrics (Owner: Ken)

  • Make sure metrics are in place and ready to point at the new environment