Knowledge Base Development Timeline

Updated: 09/10/10, postponed most things after 9/01 by 1-2 weeks

August

2nd week (9th)

  • ERD
  • Models
    • Docs
    • History
    • L10n
    • Tags
    • Category
  • Views
    • Edit
    • Read

3rd week (16th)

  • Wiki hooks
    • Include

4th week (23rd)

  • Media Gallery
    • Models
    • Frontend (not including upload process)
  • Review workflow (early by 1wk)
  • Wiki hooks
    • Templates (syntax changes and not enough details in PRD delayed this)

September

1st week (6th)

  • DjangoCon (James out)
  • Wiki hooks
    • Showfor (late by 2wk)
    • Syntax changes for templates, warnings, notes, filepaths, menus, buttons, keys

2nd week (13th)

  • Media gallery
    • Upload process
    • Video hook for wiki parser
  • L10n
  • Search
    • Stopwords
  • Start KB Tiki migration
  • Notifications (late by 2wk)
  • Permissions (late by 2wk)

3th week (20th)

  • special pages (uses search)
  • start pages from TRO
  • polls
  • theme work

4th week (27th)

  • Rebecca out
  • theme work
  • get community input
  • Community & Staff Testday Fri Sept 24th

October

1st week (4th)

  • Rebecca out
  • uTest? testday?
  • KB Discussion
  • CSP
  • Related articles/questions

2nd week (11th)

  • QA + fixing