Firefox/IterativeDevelopment/Test
Jump to navigation
Jump to search
Iteration 38.1 Performance Report
Iteration Production Goal
- Team failed to achieve the iteration production goal of 165 points and completed 142 points.
Release Production Goal
- Given the 142 points completed in IT 38.1 the team is currently behind in achieving the target release goal of 495 points for Release 38.
- The team will need to complete a minimum of 188 points in IT 38.2 to get back on track.
Production Range
- Team achieved a median velocity of 167 points with a 90% likelihood the actual points completed will fall between 70 and 254 in Iteration 38.2.
Production Growth
- The team's production range experienced a net contraction of 5.6% in comparison to the Q1 baseline:
- Minimum production capacity decreased 5.4% (4 points).
- Median production capacity decreased 1.8% (3 points).
- Maximum production capacity increased 1.6% (4 points).
Completion Rate
- 86% of iteration point target completed.
- 30% of release point target completed to date.
Completed Work
Bugzilla query error
There was a problem during the HTTP request: 429 Unknown Error