Line 62: Line 62:
! style="text-align: center;" | Status
! style="text-align: center;" | Status
|-
|-
| Milestone 1
| Red Tai FL
|
| December 15, 2015
! style="background:#00EC00;" | ON TARGET
|-
| Milestone 2
|
! style="background:#FFFF00;" | CHALLENGED
|-
| Milestone 3
|
! style="background:#FF2800;" | AT RISK
! style="background:#FF2800;" | AT RISK
|}
|}
Line 80: Line 72:
! style="text-align: center;" | Status
! style="text-align: center;" | Status
! style="text-align: center;" | Key
! style="text-align: center;" | Key
|-
! style="background:#00EC00;" |
| On Target
| The project or deliverable is expected to meet its due date.
|-
! style="background:#FFFF00;" | 
| Challenged
| The project or deliverable is facing an issue that might cause it to miss its due date, but a “get well” plan has been developed to get it back on track.
|-
|-
! style="background:#FF2800;" |  
! style="background:#FF2800;" |  
Line 93: Line 77:
| The project or deliverable is blocked or facing an issue that might cause it to miss its due date, and there’s no “get well” plan to get it back on track, or it is already late.  
| The project or deliverable is blocked or facing an issue that might cause it to miss its due date, and there’s no “get well” plan to get it back on track, or it is already late.  
|-
|-
! style="background:#00B2FF;" |
| Done
| The project or deliverable has been completed.
|-
! style="background:#C1C6CA;" |
| On Hold
| The project or deliverable has been placed on hold.
|}
|}