=='''Archived Completed Deliverables'''== | |||
{| class="wikitable" | |||
! style="text-align: center;" | Milestone | |||
! style="text-align: center;" | Date | |||
! style="text-align: center;" | Status | |||
! style="text-align: center;" | Status Notes | |||
|- | |||
| Gather feedback on the plan after discussion at 2/9 Engineering Program Review. | |||
| 2/12/16 | |||
! style="background:#00B2FF;" | Done | |||
| 2/9 review was well attended and lots of feedback was shared in the Transition of Firefox OS Code Base Proposed Plan. 2-3 additional reviews were held via videoconf. Participation was good. | |||
|- | |||
| Identify engineers to work on the code transition plan | |||
| 2/12/16 | |||
! style="background:#00B2FF;" | Done | |||
| Identified engineers' names have been inserted into the plan. We've documented which components of the plan they'll each work on and for how long. | |||
|- | |||
| Hold a final review of the proposed plan with the engineering team | |||
|2/12/16 | |||
! style="background:#00B2FF;" | Done | |||
| Final reviews held via email. | |||
|- | |||
| Present plan at weekly Engineering Program Review | |||
| 2/16/16 | |||
! style="background:#00B2FF;" | Done | |||
| Wasn't ready by the 2/16 review but plan was submitted to Faramarz 2/19 via email. | |||
|- | |||
| Present plan at All Hands | |||
| 2/25/16 | |||
! style="background:#00B2FF;" | Done | |||
| | |||
|- | |||
|} | |||
---- | ---- | ||