No edit summary |
||
Line 20: | Line 20: | ||
! style="background:#00EC00;" | On Target | ! style="background:#00EC00;" | On Target | ||
| | | | ||
* | * Team is working to define product and hardware plan by Oct 1. | ||
* | * Completed development kit evaluation and decided on linus boards with Cortex A5 processor. | ||
* Between 09/23 and 10/21, the marketing team will be doing UX interviews. | |||
* Go-to-Market communication launch moved from 9/23 to 10/21. | |||
* UX on track to provide wireframes for out of box user journey by EOW. | |||
* Project Goals: | |||
**Evidence from the experiments to show the consumer needs. (consumer service) | |||
**Defined product (kit) to be prototyped by partner (hardware solution) | |||
|- | |- | ||
| [[Connected_Devices/Projects/Project_Magnet|Project Magnet]] | | [[Connected_Devices/Projects/Project_Magnet|Project Magnet]] |