** Discussed current status of project and further plans | |||
** Decided on plans for integration with nss-try and development of Argon2 based on Blake2 | |||
* Progress | * Progress | ||
** Blake2b and Blake2s include known answer tests for keyed and unkeyed hashes | |||
** NSS Phabricator and Try server level 1 access granted | |||
* Potential points of discussion: | * Potential points of discussion: | ||
** Phabricator accounts | ** Phabricator accounts | ||
Line 65: | Line 69: | ||
** Code review | ** Code review | ||
* Upcoming work | * Upcoming work | ||
** Finish up performance testing for Blake2b and Blake2s | |||
** Merge blake2b and 2s repositories | |||
* | ** Get into integrating with NSS-Try and start with Argon2 | ||
* | |||
** | |||
** | |||