*Updated* A single release is composed of 8 weeks of development time, a 4 week stabilization period, and a release period of approximately** 1-2 weeks depending on comms/marketing plans.
'''Updated''' A single release is composed of 8 weeks of development time, a 4 week stabilization period, and a release period of approximately** 1-2 weeks depending on comms/marketing plans.


Releases overlap such that development begins on the next release when the previous release enters stabilization.
Releases overlap such that development begins on the next release when the previous release enters stabilization.