* Roundtable | * Roundtable | ||
Notes: | |||
* Server is in staging, running tests and running into issues. Perhaps LDAP problems? Still planning on being ready to push to production by Thursday/Tuesday. | |||
* Get code reviews on the refactoring by morgamic's team. Toby to send out review request before Thursday? | |||
* Ops is all done for 1.0. | |||
* Tracy to do more QA for the above test cases. | |||
* Ed will push RC 2 to AMO today. | |||
* Security review Round 1 should be done by the end of this month. | |||
* Hardware has been ordered and should be arrving in ~2 weeks. | |||
* Registration as a separate piece. | |||
* Ragavan to schedule a brain dump session with morgamic, toby, les, zandr, IT tbd. | |||
* |