Program Management/Firefox/2013-Q3-Goals: Difference between revisions

Jump to navigation Jump to search
Line 35: Line 35:
'''Team Performance'''
'''Team Performance'''
* Establish a minimum median velocity of 50 (Expected Date of Completion) and an actual velocity range that falls between 46 (Pessimistic Date of Completion) and 63 (Optimistic Date of Completion) by the conclusion of Iteration #15.
* Establish a minimum median velocity of 50 (Expected Date of Completion) and an actual velocity range that falls between 46 (Pessimistic Date of Completion) and 63 (Optimistic Date of Completion) by the conclusion of Iteration #15.
** At the conclusion of Iteration #10, given the historical velocity performance values of 30,32,33,46,51,63,68,74,75,75, the Metro Team has a median velocity of 57 and there is a 90% likelihood that the actual velocity will fall between 32 and 75.
* Given a forecasted growth to 127 defects/changes from Iteration #10 - #15, the Metro Team will resolve enough defects/changes to ensure the Defect & Change Backlog does not exceed more than 79 defects/changes (not including 'on-hold' items) by the conclusion of Iteration #15 .
* Given a forecasted growth to 127 defects/changes from Iteration #10 - #15, the Metro Team will resolve enough defects/changes to ensure the Defect & Change Backlog does not exceed more than 79 defects/changes (not including 'on-hold' items) by the conclusion of Iteration #15 .
** At the conclusion of Iteration #10 the Defect & Change Backlog totalled 61 defects/changes (not including 'on-hold' items)