For each quarter, there are 12 work weeks, with roughly 480 work hours (per person).
=== Communicate with Graphics team ===
=== Communicate with Graphics team ===
* Discuss with Graphics team about each active features for FxOS (from [https://docs.google.com/a/mozilla.com/spreadsheet/ccc?key=0AnKFEBp1-VyqdFNfRlZmV0ExM0VvZGMxNThWX0d6LWc&usp=drive_web#gid=0 graphics features backlog]) for possible areas of weakness and test strategy. When a feature becomes active and FxOS relevant, it should be discussed.  Record findings in Bugzilla and use them for testing when the feature is completed.  
* Discuss with Graphics team about each active features for FxOS (from [https://docs.google.com/a/mozilla.com/spreadsheet/ccc?key=0AnKFEBp1-VyqdFNfRlZmV0ExM0VvZGMxNThWX0d6LWc&usp=drive_web#gid=0 graphics features backlog]) for possible areas of weakness and test strategy. When a feature becomes active and FxOS relevant, it should be discussed.  Record findings in Bugzilla and use them for testing when the feature is completed.  
Line 82: Line 81:
* Resource Estimate: 40 hrs
* Resource Estimate: 40 hrs
* Deliverable: Check-ins in Git repository, Update [https://developer.mozilla.org/en-US/docs/Mozilla/QA/Marionette/Run_ImageMagick_Tool_with_Python_Marionette wiki]
* Deliverable: Check-ins in Git repository, Update [https://developer.mozilla.org/en-US/docs/Mozilla/QA/Marionette/Run_ImageMagick_Tool_with_Python_Marionette wiki]
=== Areas Not Covered ===
Following areas are not covered by this plan:
* Graphics [https://developer.mozilla.org/en-US/Firefox_OS/Platform/Automated_testing/Reftests Mochitests] [https://developer.mozilla.org/en-US/docs/Mochitest / Reftests]
* Graphics [https://developer.mozilla.org/en-US/Apps/Build/Performance/Firefox_OS_performance_testing performance measurements] (e.g. APZ performance, FPS for image rendering, etc.)


'''Total estimated hours: 208 hours (approximately 40~50% of one person workload for the quarter)
'''Total estimated hours: 208 hours (approximately 40~50% of one person workload for the quarter)