Releases/Thunderbird 3.0b2/Post Mortem: Difference between revisions
Jump to navigation
Jump to search
No edit summary |
(→QA) |
||
Line 21: | Line 21: | ||
=== Release Notes === | === Release Notes === | ||
=== Build === | === Build === | ||
=== QA === | === QA === | ||
* Need to avoid mixing Litmus runs and Test Days - as it confuses people. This should be fixed with better communication (see 2.1 above). | |||
* Need to run upgrade from previous version tests to avoid things like {{bug|480556}}. | |||
== Anything else == | == Anything else == | ||
* need to firm up crash-stats.m.c update step, seems to be insufficient to ask for adding the release and next development release. ref {{bug|480728}} MTBF missing Thunderbird 3.0b2 milestone, and development 3.0b3pre & 3.1a1pre // 3.0b2 topcrash no results | * need to firm up crash-stats.m.c update step, seems to be insufficient to ask for adding the release and next development release. ref {{bug|480728}} MTBF missing Thunderbird 3.0b2 milestone, and development 3.0b3pre & 3.1a1pre // 3.0b2 topcrash no results | ||
== Actions == | == Actions == | ||
== Attendees == | == Attendees == |
Revision as of 07:17, 2 March 2009
Yes, this is currently a post mortem before the patient has passed.
Post Mortem for the Thunderbird release of 3.0b2
What went well
What could have gone better, and lessons learned
Leading up to the release
- In reference to the Development Page page.
- Weekly milestones are necessary
- Create a milestone for every week in release cycle
- Name milestones: ${REL}week${NUM} ex: b2week1, b2week2, etc
- Plan landing of items (features/bugs) in each week
- Set status whiteboard of bugs with milestone names (makes them searchable)
- Work with Q/A to plan sessions testing milestone one week after it lands
- Create search links for each week milestone
- Release dates should have indicator of strength
- Something like keywords strong, weak, or likely to slip to communicate how solid the dates are at this point
- Weekly milestones are necessary
- should release process planning meeting be removed from 3.0b2? (hasn't been done for last 2 releases) Should it simply be replaced with references to prior releases' postmortems?
String Freeze
Code Freeze
Release Notes
Build
QA
- Need to avoid mixing Litmus runs and Test Days - as it confuses people. This should be fixed with better communication (see 2.1 above).
- Need to run upgrade from previous version tests to avoid things like bug 480556.
Anything else
- need to firm up crash-stats.m.c update step, seems to be insufficient to ask for adding the release and next development release. ref bug 480728 MTBF missing Thunderbird 3.0b2 milestone, and development 3.0b3pre & 3.1a1pre // 3.0b2 topcrash no results