AMO/FlightDeck/Roadmap/2012
![]() |
Web Builder 2012 Roadmap | |
Owner: Daniel Buchner | Updated: 2012-01-17 | |
For 2012, we will be working on two primary initiatives: launching the Add-on Builder website in its current state and transitioning the product to a more generic Web Builder to support rapid development of all developer-facing Mozilla platforms (add-ons, apps, etc.) |
MISSION: Enable rapid development for our application platforms
Provide web developers with a robust, browser-based environment that makes creation, publishing, and maintenance of Mozilla product platform applications dead simple.
Q1 2012 - Launch the Add-on Builder website
Description
In its first publicized release, the Add-on Builder will be launched as a website under the AMO domain. The application will undergo hardening and extensive triage during the month of January. In parallel, we will be working with Marketing and PR to generating a marketing plan that targets a much broader audience of developers from those who have never developed an add-on to those who do it professionally.
When the Add-on Builder team, and associated stakeholders, agree the product has reached a 1.0 launch-ready state, we will solidify a launch date (initial target is mid February), and begin executing our marketing plan.
The team will reserve the entire week following the launch to monitor the product. During this post-launch monitoring period, all members of the primary Builder team will be on-call to address any issues that may arise.
Goals & Actions
- Develop 1.0 test plan - mid January
- Develop 1.0 marketing plan - mid January
- Launch and triage the Add-on Builder 1.0 release - mid February
- Begin blueprinting the structure of the Builder as an app - late February
Q2/Q3.5 2012 - Implement the Builder as a modular app
Description
In its first publicized release, the Add-on Builder will be launched as a website under the AMO domain. The application will undergo hardening and extensive triage during the month of January. In parallel, we will be working with Marketing and PR to generating a marketing plan that targets a much broader audience of developers from those who have never developed an add-on to those who do it professionally.
When the Add-on Builder team, and associated stakeholders, agree the product has reached a 1.0 launch-ready state, we will solidify a launch date (initial target is mid February), and begin executing our marketing plan.
The team will reserve the entire week following the launch to monitor the product. During this post-launch monitoring period, all members of the primary Builder team will be on-call to address any issues that may arise.
Goals & Actions
- Develop the structural/foundation Builder app code - late March
- Implement a system for extending the basic Builder app - early May
- Develop an extension package to support the Add-on SDK project type - early June
- Move Add-on/Library search into Add-on SDK project type - early June
- Expose the Add-on/Library search on a Mozilla web property - early June
- Implement a system for discovering new Builder extensions - early July
- Release a preview of the appified Builder on the app/add-on market - early September
- Surface Builder UI touch-points in Firefox - early October
Q4 2012 - Ready the new Add-on Builder app for launch in Firefox
Description
In its first publicized release, the Add-on Builder will be launched as a website under the AMO domain. The application will undergo hardening and extensive triage during the month of January. In parallel, we will be working with Marketing and PR to generating a marketing plan that targets a much broader audience of developers from those who have never developed an add-on to those who do it professionally.
When the Add-on Builder team, and associated stakeholders, agree the product has reached a 1.0 launch-ready state, we will solidify a launch date (initial target is mid February), and begin executing our marketing plan.
The team will reserve the entire week following the launch to monitor the product. During this post-launch monitoring period, all members of the primary Builder team will be on-call to address any issues that may arise.
Goals & Actions
- Develop and execute appified Builder test plan - late October
- Develop and begin appified Builder marketing plan - late October
- Launch and triage the Web Builder 1.0 release - late November